Compute the value-added ratio

Assignment Help Managerial Accounting
Reference no: EM132767755

Problem - Lead Time - The Swift Mountain Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 30-ski batch sizes. The finishing time is 14 minutes per ski. The assembly time is 10 minutes per ski. It takes 8 minutes to move a batch of skis from finishing to assembly.

Required -

a. Compute the value-added, non-value-added, and total lead time of this process.

b. Compute the value-added ratio. Round to one decimal place.

Reference no: EM132767755

Questions Cloud

Understanding of wan to wan connections : Explain your basic understanding of WAN to WAN connections, LAN to LAN connections, and WAN to LAN connections.
Determine the inspection activity cost per unit : Lexter Company incurred an activity cost of $180,000 for inspecting 25,000 units of production. Determine the inspection activity cost per unit
What are the techniques currently used to build models : How is the model-based policy design different from intuitive policy making? What are the techniques currently used to build models?
Explain the historical development of public health : Imagine you have been asked by your local government to help create a newsletter for your community. For the first issue, they have asked you to provide.
Compute the value-added ratio : Skis are manufactured in 30-ski batch sizes. The finishing time is 14 minutes per ski. Compute the value-added ratio
Century of population explosion and fossil fuel burning : The authors assert that the twentieth century is considered as the century of population explosion and fossil fuel burning, environmental policies
Journalize the entry to record the costs transferred : The conversion cost for 2,400 hours of production is budgeted for the year at $4,800,000. Journalize the entry to record the costs transferred
What is the cost to be debited to finished goods : The cell started and completed 700 units. The cell process time for the product is 15 minutes per unit. What is the cost to be debited to Finished Goods
Journalize entries for the conversion costs : Lean Accounting - The budgeted conversion costs for a lean cell are $142,500 for 1,900 production hours. Journalize entries for the conversion costs

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd