Compute the total slack for each activity

Assignment Help Project Management
Reference no: EM131782658

Assignment

Compute the project network sequence and proper timing to complete the project using an excel spreadsheet, PowerPoint, or another appropriate form of delivery method. Address all required information in the description below. In addition, respond to the following questions (300-500 words):

1. Provide the Early Start, Early Finish, Late Start, and Late Finish times for each activity. Compute the Total Slack for each activity. Determine which activities are on the critical path. How long will it take to complete the project?

2. An activity that is on the critical path for this project has increased by 7. Will the project end date be delayed? If so, by how much?

You are creating a customer database for the Modesto Nuts minor leaguebaseball team. Draw a project network given the information below. Completethe forward and backward pass, compute activity slack, and identify thecritical path.How long will this project take? How sensitive is the network schedule?Calculate the free slack and total slack for all noncritical activities.

ID   Description                              Predecessor          Time (days)
A    Systems design                        None                        2
B    Subsystem A design                 A                              1
C    Subsystem B design                 A                              1
D    Subsystem C design                  A                             1
E     Program A                               B                              2
F     Program B                               C                              2
G    Program C                               D                              2
H    Subsystem A test                     E                              1
I     Subsystem B test                     F                              1
J     Subsystem C test                     G                             1
K    Integration H, I,                        J                              2
L    Integration test                         K                             1

Reference no: EM131782658

Questions Cloud

What is omega after-tax wacc : Omega Corporation has 10 million shares outstanding, now trading at $55 per share. What is Omega's after-tax WACC
Describing the modifier method : You could check the invariant in each modifier method just before it returns and throw an exception if the invariant fails.
What interest rate is needed to make : We can use the formula A = P(1 + r)2 to find the amount $A that $P will become when invested at an annual rate of r% for two years.
Compute the margin and turnover ratios for the division : Conceptual Connection: Compute the margin and turnover ratios for the division with the new investment
Compute the total slack for each activity : Compute the Total Slack for each activity. Determine which activities are on the critical path. How long will it take to complete the project?
Convert a temperature of c degrees on the celsius scale : The boiling point of water is 212° on the Fahrenheit scale and 100° on the Celsius scale. The freezing point of water is 32° on the Fahrenheit scale.
What amount of unrelaized gross profit must panner defer : What amount of unrelaized gross profit must Panner defer in reporting this investment using the equity method
Calculate and display the largest number : Calculate and display the largest number, the smallest number, and the range (largest number - smallest number) for any given set of numbers between two values.
Produce the appropriate classification for given : A certain city classifies a pollution index of less than 35 as pleasant, 35 through 60 as unpleasant, and above 60 as hazardous.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd