Reference no: EM132609767
Question - The following data pertain to the activities of a general contractor:
Total billings for the accomplishments for the period:
Service fee inclusive of VAT - 336,000
Construction supplies sold (VAT included) - 28,000
Actual amount collected for services rendered - 168,000
Total payments made to VAT persons for the period:
Construction supplies suppliers - 112,000
Sub-contractors (VAT Registered) - 56,000
Required - Compute for the following
a. Total output VAT for the period.
b. Total input VAT for the period.
c. Net VAT payable (to be remitted).