Compute the total direct materials cost variance

Assignment Help Managerial Accounting
Reference no: EM132514655

Karloff reports the following for one of its products.

Direct materials standard (3 lbs. @ $5 per lb.)       $15 per finished unit

Actual finished units produced                               100,000 units

Actual cost of direct materials used                             $1,430,000

Question 1: Compute the total direct materials cost variance, price variance, and quantity variance and classify them as favorable or unfavorable.

Reference no: EM132514655

Questions Cloud

Build journal entries to record the transactions : Of this amount, $46,000 is classified as indirect labor and the remainder as direct. Prepare journal entries to record these transactions.
Prepare journal entries to record the three transactions : $11,000 of raw materials indirectly as factory supplies and uses $84,800 of raw materials . Prepare journal entries to record three transactions
What is ending raw materials inventory balance for march : During the month were $141,900 of direct materials and $13,100 of indirect materials. What is the ending Raw Materials Inventory balance for March?
Analyze the importance of effective planning : Analyze the importance of effective planning and control measures in each stage of the project management life cycle. Fairness within an organization.
Compute the total direct materials cost variance : Compute the total direct materials cost variance, price variance, and quantity variance and classify them as favorable or unfavorable.
What would be the total unavoidable costs : What would be the total unavoidable costs? The facility wide costs only at $22,000, or would the value of the building be included even if it was sold?
Ethical business decision making to balance corporate : Determine the considerations for and process of ethical business decision making to balance corporate and social responsibilities, and address moral, economic,
Describe the methods used in recruitment efforts : For this assignment, imagine you will be presenting at a conference for an audience of newly hired human resource professionals. You are to share your knowledge
BSBCUS501 Manage Quality Customer Services Assignment : BSBCUS501 Manage Quality Customer Services Assignment Help and Solution, Australian Centre of Further Education - Assessment Writing Service

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd