Reference no: EM132515140
Maryville Manufacturing
Maryville Manufacturing designs and builds custom mudroom storage benches. All of the mudroom storage benches are constructed with rustic hickory. Its budgeted manufacturing costs for the 2018 year are as follows.
Overhead Cost Pools Amount
Purchasing $ 45,000
Handling materials $ 50,000
Production (cutting, milling, finishing) $130,000
Setting up machines $ 85,000
Inspecting $ 60,000
Inventory control (raw materials and finished goods) $ 80,000
Utilities $ 100,000
Total budgeted overhead costs $550,000
- For the last 5 years, Maryville Manufacturing has been charging overhead to products on the basis of materials cost. For the year 2018, materials cost of $500,000 were budgeted.
- Jim Johnson, owner-manager of Maryville Manufacturing, recently directed his accountant, Ledger Kaufman, to implement the activity-based costing system that he has repeatedly proposed. At Jim's request, Ledger and the production foreman identify the following cost drivers and their usage for the previously budgeted overhead cost pools.
Overhead Cost Pools Activity Cost Drivers Expected Use of Cost Drivers
Purchasing Number of orders 500
Handling materials Number of moves 5,000
Production (cutting, milling, finishing) Direct labor hours 65,000
Setting up machines Number of setups 1,000
Inspecting Number of inspections 4,000
Inventory control (raw materials and finished goods) Number of components 40,000
Utilities Square feet occupied 50,000
- Doug Russell, sales manager, has received an order for 12 custom mudroom storage benches from Homes by Kathy. At Doug's request, Ledger prepares costs estimates for producing 12 mudroom storage benches so Doug can submit a contract price per mudroom storage bench to Homes by Kathy. He accumulates the following data for the production of 12 mudroom storage benches.
Direct materials $5,200
Direct labor $3,500
Direct labor hours 200
Number of purchase orders 3
Number of material moves 32
Number of machine setups 4
Number of inspections 20
Number of components 640
Number of square feet occupied 320
Required:
Question 1. Compute the predetermined overhead rate using traditional costing with direct materials cost as the allocation base.
Question 2. Compute the total cost of manufacturing one mudroom storage bench using direct materials cost as the allocation base for manufacturing overhead.
Question 3. Compute the predetermined overhead rate using traditional costing with direct labor hours as the allocation base.
Question 4. Compute the total cost of manufacturing one mudroom storage bench using direct labor hours as the allocation for manufacturing overhead.
Question 5. Compute the predetermined overhead rate per cost driver for each of the overhead cost pools using the proposed activity-based costing system.
Question 6. Compute the total cost of manufacturing one mudroom storage bench using the proposed activity-based costing system.
Question 7. Which allocation base is preferable under traditional costing and why?
Question 8. Which costing system (traditional or activity-based) is preferable in pricing decisions and why?
Question 9. What would a formal memo addressed to the owner of the company that includes a recommendation related to the adoption of activity-based costing.