Compute the price and quantity variances for direct material

Assignment Help Managerial Accounting
Reference no: EM131706712

Pace Labs, Inc. provides mad cow disease testing for both state and federal governmental agricultural agencies. Because the company's customers are governmental agencies, prices are strictly regulated. Therefore, Pace Labs must constantly monitor and control its testing costs. Shown below are the standard costs for a typical test.

Direct materials (2 test tubes @ $1.46 per tube)

$ 2.92

Direct labor (1 hour @ $24 per hour)

24.00

Variable overhead (1 hour @ $6 per hour)

6

Fixed overhead (1 hour @ $10 per hour)

10

    Total standard cost per test

$42.92

The lab does not maintain an inventory of test tubes. Therefore, the tubes purchased each month are used that month. Actual activity for the month of November 2014, when 1,500 tests were conducted, resulted in the following:

Direct materials (3,050 test tubes)

$ 4,209

Direct labor (1,600 hours)

36,800

Variable overhead

7,400

Fixed overhead

15,000

Monthly budgeted fixed overhead is $14,000. Revenues for the month were $75,000, and selling and administrative expenses were $5,000.

Compute the price and quantity variances for direct materials and direct labor.

Compute the total overhead variance.

Prepare an income statement for management.

Reference no: EM131706712

Questions Cloud

Describe your vision for working with your mentees : Develop an Individual Development Plan. Write a brief vision statement (250-500 words) describing your vision for working with your mentee(s).
Attorney general and innocence project recommendations : Do you agree with the Attorney General and Innocence Project recommendations
Find the present value of an investment : The future value in three years of $1,000 deposited today in a savings account with interest compounded annually at 8 percent
The dangers concerned with its productions and interdiction : What is the newest, very common drug (illegal/illicit) to be manufactured in the United States. What methods and places are used to manufacture it
Compute the price and quantity variances for direct material : Compute the total overhead variance - Prepare an income statement for management - Compute the price and quantity variances for direct materials
How much you would be willing to pay for it today : Then you must use this value to determine how much you would be willing to pay for it today! So, Step 1 is to find the value of the bond in 6 years -> N=14,...)
Why is reputation so important to an organization : Why is reputation so important to an organization? Answer the following questions. Is it true that when the reputation of one company suffers.
Define warrant on an apartment for stolen property : Would it ever be necessary to apply the plain view doctrine while executing a valid search warrant on an apartment for stolen property
What is the fixed monthly payment : What is the fixed monthly payment you will have to make? Write out the amortization table for this loan for the first three months of the loan.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd