Question - Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units.
Actual run time this week 6,636 minutes
Machine time available per week 7,900 minutes
Actual run rate this week 1.78 units per minute
Ideal run rate 2.00 units per minute
Defect-free output this week 11, 696 units
Total output this week (including defects) 13,600 units
Required -
1. Compute the utilization rate.
2. Compute the efficiency rate.
3. Compute the quality rate.
4. Compute the overall equipment effectiveness (OEE).