The following questions all concern a proposal to build a dam to reduce the chances that farmers will be subject to flooding and to increase the availability of water for farm irrigation. Assume that the cost of building the dam is predicted to be $40 million, that net benefits from the dam are predicted to be $6.0 million during each of the 100 years that the dam is expected to operate, and that at the end of the 100 years the dam has no salvage value.
a. Is the option value of the dam likely to be positive, negative, or zero? Briefly explain.
b. Compute the net present value of the dam, assuming that annual net benefits are received at the end of each year. In making this computation, use the conventional approach to discounting and a discount rate of 8 percent. [Please show your work clearly so that I can give you partial credit if it is appropriate to do so.]
c. Does it matter whether the 8 percent discount rate you just used was based on a real or a nominal interest rate? Which should you be using? Briefly explain.
d. Suppose there is uncertainty surrounding the values you used to compute the net present value of the dam in (b). Specifically, benefit-cost analysts believe the discount rate could be as high as 10 percent or as low as 5 percent, the initial cost of building the dam could be as high as $45 million or as low as $35 million, and annual net benefits could be as high as $7 million or as low as $5 million. Given your answer to (b), indicate whether a best-case analysis or a worst-case sensitivity analysis is more appropriate, make the calculations required to do the analysis you selected, and briefly discuss what your calculations imply about whether the dam should be built.
e. Re-compute the net present value of the dam using the shadow price of capital method. In doing this, again assume that the dam would cost $40 million to build and generate annual benefits of $6 million. Also assume that the social rate of time preference is 3 percent and that the shadow price of capital is 2.0. Further assume that all of the costs of building the dam displace private sector investment and that 20 percent of annual net benefits from the dam flows into investment and 80 percent flows into consumption. [Again, please clearly show your work.]
f. Because the dam would produce water for irrigation, it would increase the productivity of the farms using the water. One can think of this new source of water as shifting the supply curve of, say, wheat downward. Assume that the price of wheat is artificially supported at a level above the competitive market price, and that this higher price, which is called a "target price," is the one farmers look to in making their production decisions. Wheat is sold at the price required to induce consumers to purchase all that farmers produce. The government uses tax revenues to pay farmers the difference between this price and the target price. Would building the dam cause the tax revenues paid to farmers to increase or decrease? Use a graph to demonstrate this.
Discount rate be before you would reject the project
: A new computer system will require an initial outlay of $17,000, but it will increase the firm’s cash flows by $3,400 a year for each of the next 7 years. Calculate the NPV and decide if the system is worth installing if the required rate of return i..
|
Discussion: pharmacotherapy for respiratory disorders
: Discussion: Pharmacotherapy for Respiratory Disorders. Select and research one of the following respiratory disorders: the common cold, pneumonia, or a chronic obstructive pulmonary disease (COPD) such as emphysema or chronic bronchitis
|
What is the current price of the stock
: Ginger Baker, Inc. just paid an annual dividend of $3 a share and this dividend is expected to grow at a rate of 4% per year for the foreseeable future. If the discount rate for Ginger Baker is 9%, what is the current price of the stock?
|
What is the process of dna replication
: What is the process of DNA replication? Please include descriptions and possibly diagrams to further explain the process.
|
Compute the net present value of the dam
: The following questions all concern a proposal to build a dam to reduce the chances that farmers will be subject to flooding and to increase the availability of water for farm irrigation Compute the net present value of the dam, assuming that annual ..
|
What is the project''s net present value
: An additional $4,000 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 11 percent
|
Implementing ebp in the health care field
: What are some of the obstacles or barriers to implementing EBP in the health care field? Provide a rationale for your answer. Since there are numerous topics on the issue, it is not appropriate to repeat one that has already been mentioned unless ..
|
What was average nominal risk premium on crash-n-burn stock
: You’ve observed the following returns on Crash-n-Burn Computer’s stock over the past five years: 4 percent, -12 percent, 26 percent, 16 percent, and 16 percent. The average inflation rate over this period was 3.6 percent and the average T-bill rate w..
|
What are advantages and disadvantages of residual policy
: Information Systems Technology (IST), which develops software for the health care industry, was founded five years ago by Donald Brown and Margaret Clark, who are still its only stockholders. What are the advantages and disadvantages of the residual ..
|