Reference no: EM132802382
Question - A company has provided the following data concerning one of the products in its standard cost system.
Inputs Standard Quantity per unit of Output Standard Price
Direct materials 8.0 ounces $8.10/ounce
The company has reported the following actual results for the product for April:
Actual output 6,500 units
Raw materials purchased 62,350 ounces
Actual cost of raw materials purchased $386,210
Raw materials used in production 52,020 ounces
Required -
A) Compute the materials price variance for April.
B) Compute the materials quantity variance for April.