Reference no: EM132585280
Waterways uses time and material pricing when it bids on irrigation projects. Budgeted data for the coming year are as follows.
WATERWAYS CORPORATION
Budgeted Costs for Irrigation ProjectsTime
Charge Material
Loading
ChargesLabor wages (5,700 hours) $238,260
Supervisor's salary $58,000
Clerical and accountant wages 58,1404,000
Irrigation supplies manager 38,000
Overhead 55,86018,800
Total $352,260
$118,800
Waterways has budgeted for 5,700 labor hours. It desires a $14 profit margin per hour of labor and 18% profit on materials. It estimates the total invoice cost of materials in the coming year will be $660,000.
Question 1: Compute the rate per hour of labor. (Round answer to 2 decimal places, e.g. 52.75.)
Question 2: Compute the material loading charge
Question 3: Waterways has received a request for a bid to do parkway for the city. The irrigation manager estimates that it will take about a month to complete the project and require 450 hours of labor and $79,000 of materials Compute the total estimated bid for the parkway project. (Round answer to 0 decimal places, e.g. 5,275.)