Problem - Comprehensive Variance Analysis - Marvel Parts, Inc., manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,035 hours each month to produce 2,070 sets of covers. The standard costs associated with this level of production are:

 

Total

Per Set of Covers

Direct materials

$31,878

$15.40

Direct labor

$6,210

3.00

Variable manufacturing overhead (based on direct labor-hours)

$4,347

2.10

 

 

$20.50

During August, the factory worked only 500 direct labor-hours and produced 1,700 sets of covers. The following actual costs were recorded during the month:

 

Total

Per Set of Covers

Direct materials (5,000 yards)

$25,500

$15.00

Direct labor

$5,440

3.20

Variable manufacturing overhead

$4,080

2.40

 

 

$20.60

At standard, each set of covers should require 2.0 yards of material. All of the materials purchased during the month were used in production.

Required -

1. Compute the materials price and quantity variances for August.

2. Compute the labor rate and efficiency variances for August.

3. Compute the variable overhead rate and efficiency variances for August.

Reference no: EM133052177

Questions Cloud

Create a role-play script : After reviewing appendix 1 and 2, create a role-play script in regards to discussing the details you have provided above.
What is the amount of the principal reduction : On January 1, 2020, Hilton Inc. received a $100,000, 5%, 10-year bank loan. What is the amount of the principal reduction
Contrast the two general types of stress : Compare and contrast the two general types of stress. Include an example of each.
Compute the expected returns on the factor portfolios : Suppose that there are two independent risk factors F1 and F2. Thus, a two-factor model for portfolio i is given by ri = E[ri] + ßi1F1 + ßi2F2+ ei.
Compute the labor rate and efficiency variances for August : During August, the factory worked only 500 direct labor-hours and produced 1,700 sets of covers. Compute the labor rate and efficiency variances for August
Elements of management ideas : Despite the fact that elements of management ideas and practice can be found in ancient civilizations, management did not really become a field of study until a
Managing a supply chain so challenging : How many weeks did it take you to bring the supply chain back into equilibrium?
Expansion strategy focus on developing nations : Why did Tesco's initial international expansion strategy focus on developing nations?
How would you respond to inventory shortage : How would you respond to this inventory shortage? What changes would you make to your business

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd