Compute the factory overhead volume variance.

Assignment Help Accounting Basics
Reference no: EM13189358

The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit.  The variable overhead rate was $3 per hour. Actual fixed overhead was $360,000 and actual variable overhead was $170,000. Actual production was 11,700 units.

Compute the factory overhead volume variance.
Answer

A.$9,000F

B.$9,000U

C.$5,500F

D.$5,500U

Reference no: EM13189358

Questions Cloud

What is the nominal interest rate is the bank paying : A bank announces that it has changed its interest computation method to continuous compounding. Now $2000 left in the bank for 9 years will double to $4000. What is the nominal interest rate, compounded continuously, is the bank paying.
How can equations and inequalities help a business : how can equations and inequalities help a business maximize profit or minimize costs? What is the importance of understanding hoe to set up and solve equations and inequalities.
What are the unions and intersections of both : if a union b of z
What is the straight line distance : If Tom Bombadil's house is 24 miles east of Hobbiton and 32 miles south, what is the straight line distance.
Compute the factory overhead volume variance. : The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit.
How does the banks findiing relate to economists : To try to determine what fee customers were willing to pay for expedited payments, the bank conducted a survey. It was able to determine that many of the people surveyed already paid fees for expedited payment services that exceeded the maximum fe..
Why courts invariably throw out cases : Courts invariably throw out cases like hers. They are, however, willing to entertain suits against trade schools (those that teach skills such as welding and computer repair) by guarantee that make the same claims about inability to qualify for jo..
Develop an activity diagram for the use case : Develop an Activity Diagram for the use case chosen in part A and develop a System Sequence Diagram (SSD) for the complete overall system and a Sequence Diagram (SD) for your selected use case.
The amount of the direct labor rate variance : The standard costs and actual costs for direct labor for the manufacture of 2,500 actual units of product are as follows:

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd