Compute the expected duration and variance

Assignment Help Operation Management
Reference no: EM13103769 , Length: 2500 Words

A network consists of the following list. Times are given in weeks.

Activity

Preceding

Optimistic

Probable

Pessimistic

A

--

2

3

4

B

A

4

4

8

C

A

3

5

7

D

B

5

5

5

E

B,C

3

6

7

F

D

4

5

9

G

E, F

3

3

7

a.             Draw the network diagram.

b.        Calculate the expected duration and variance of each activity.

c.         Calculate the expected duration and variance of the critical path.

d.        Calculate the probability that the project will be completed in less than 24 weeks.

 

 

Reference no: EM13103769

Questions Cloud

Discuss the objective of critical path analysis : What is the objective of critical path analysis? Explain why the critical path is the longest, not the shortest, path through a network.
Lifetimes of a shipment : Testing indicates that the lifetimes of a shipment of disposable butane lighters are normally distributed with a mean of 1000 lights and a standard deviation of 100. What percentage of these lighters will:
Probabilities of ncaa basketball tournament : NCAA Basketball Tournament. Each year, 64 college basketball teams compete in the NCAA tournament. Sandbox.com recently offered a prize of $10 million to anyone who could correctly pick the winner in each of the tournament games.
Actual weights of chocolate bars : Chocolate bars produced by a certain machine are labeled with 16.0 oz. The distribution of the actual weights of these chocolate bars is Normal with a mean of 16.1 oz and a standard deviation of 0.1 oz. A chocolate bar is considered underweight if..
Compute the expected duration and variance : A network consists of the following list. Times are given in weeks. Calculate the expected duration and variance of each activity.
Find the distance the plane moves : A steam catapult launches a jet aircraft from the aircraft carrier John C. Stennis, giving it a speed of 210 mi/h in 3.00 s. (a) Find the average acceleration of the plane. m/s2 (b) Assuming the acceleration is constant, find the distance the plan..
Explain binomial probabilities : Based on p=.60, probability that a randomly selected homeowners will say no to newspaper subscription.
Calculate the expected project completion time : Consider a project having the following ten activities. Draw a network diagram. What is the expected project completion time?
Topic on probability : The condition for the question is that the deck of cards has 52 cards and among them are 12 face cards. What is the probability of choosing 6 face cards out of 8 chosen. Thru Binomial distribution holds( meaning with replacement)

Reviews

Write a Review

Operation Management Questions & Answers

  Can you give examples where you will use only domestic

Can you give examples where you will use only domestic outsourcing providers versus situations where you will use only offshore providers

  Linear program has multiple optimal solutions

What is the optimal solution? You should be able to determine this by inspection. If the linear program has multiple optimal solutions, identify the optimal solution set.

  How you would determine the price of the product

Be sure to include how you would determine the price of the product, distribution channels, promotions, and campaign evaluation points

  The presenting problem or specific request for help

The presenting problem or specific request for help. 2. Any other problems or concerns that might need to be addressed if an ongoing relationship were to occur

  Calculate average number of customer waiting

Andrew the barber owns a four chai shop. andrew estimated that each barber would take an average of 30 min to give a haircut in an exponentially distribution fashion.

  Face-to-face meetings sometimes force work to be completed

Face-to-face meetings sometimes force work to be completed as an ancillary benefit of the social interaction

  Operational overview of the segment

ch student will be required to complete a term paper outlining a specific segment of interest within the hospitality and tourism industry. The parts of the paper should include the following information:

  Role of the human resource manager in the company

Why might this be the case? If you were human reource specilaist interviewing with this company for an open position, what would this practice imply for the role of the human resource manager in thar company?

  Cowboy saddle company manufactures plastic saddles

The Cowboy Saddle Company manufactures plastic saddles that are used in the assembly process of their Mr. Ed doll. If the run time for producing a batch of saddles is 4 days

  Illustrate what capacity requirement should be planned

If demand is expected to be 75 percent of current level in 5year and management needs to have a capacity cushion of just 5 percent, illustrate what capacity requirement should be planned.

  Describe how an organization might select an organizational

Describe how an organization might select an organizational development practitioner, noting what criteria are important to evaluate.

  Do you agree with the jury that she was guilty be-yond

Do you agree with the jury that she was guilty be-yond reasonable doubt of the conspiracy and obstruction of justice charges? was her punishment, including both imprison-ment and fines, appropriate?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd