Shining Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $800,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000.
The following data pertain to the construction period.
2020. 2021 2022
Costs to date $270,000 $450,000 $600,000
Estimated costs to complete 330,000 250,000 -0-
Progress billings to date 270,000 550,000 900,000
Cash collected to date 240,000 500,000 900,000
Instructions
Problem a. Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
Problem b. Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.