Question - During May, Joliet Fabrics corporation manufactured 500 units of a special multilayer fabric with the trade name Stylex. The following information from the StyleX production also pertains to May.
Direct material purchased 18,000 yds @ 1.38 per yard $24,840
Direct material used 9,500 yds @ 1.38 per yard $13,110
Direct Labor 2,100 hrs @ 1.95 per hour $19,215
The standard prime cost for I unit of StyleX is as follows:
Direct Material 20 yds @ 1.35 per yard $27
Direct Labor 4 hrs @ $9.00 per yard $36
Total Standard Prime cost per unit of output $63
Required - Compute the following variance for the month of May, indicating weather each variance is favorable or unfavorable.
1. Direct-Material price variance
2. Direct-Material quantity variance
3. Direct-material purchase price variance
4. Direct-Labor rate variance
5. Direct-labor efficiency variance
5. Direct-labor efficiency variance