Reference no: EM13868876
Situation: A two-span pedestrian walk-way bridge is made up of a series of 24×36 inchrectangular section beams of 42 feet span each, as shown in the figure. The center-to-center spacing between these beams is 8 feet. A 6-inch thick slab rests on these beams. The slab is not monolithically cast with beams. Criteria: The load consists of 20 psf superimposed dead load and 100 psf live load. Use fy =60,000 (for flexure design), and f'c = 4,000 psi for all calculations.
Required: Using the load given and considering that only the dead load and live load combination will be critical,
(a) Compute the design factored load (wu) for the slab and (qu) for a typical beam.
(b) Show the bending moment and shear diagram for a typical (two-span) beam under a uniform load qu.
(c) Using the value in Part (a) and the bending diagram in Part (b), compute the maximum design negative and positive moments (Mu).
(d) Design flexural reinforcement for the entire beam. Note: steel design is needed for positive moment (midspan) and negative moment (support).
(e) Show a sketch for the reinforcements you designed.
(f) As expected, the slab is a simply supported and has a span of 8 feet. We plan to use #3 steel for the slab. Design reinforcement for the slab using the load you computed in Part (a); and show a detail for the reinforcement you designed.
Why might covered interest parity fail to hold deposits
: The text points out that covered interest parity holds quite closely for deposits of differing currency denominations issued. Why might covered interest parity fail to hold when deposits issued in different ?nancial centers are compared?
|
The depreciation expense during the current year
: Turnip Company purchased an asset at a cost of $10,000 with a ten year life during the current year. The company uses differing depreciation methods for financial reporting and income tax purposes.
|
Derive the storm hydrograph
: The ordinates of a 3hr unit hydrograph of a basin at 6 hr interval are given below. You are required to derive the storm hydrograph due to a 3 hr storm with a total rainfall of 15 cm. Assume an initial loss of 0.5 cm and aφindex of 1 cm/ hr. Ta..
|
What do you think is the rationale for the regulations
: Similarly, Fed reserve requirements are imposed on any loan from a U.S. bank's foreign branch to a U.S. resident, or on any asset purchase by the branch bank from its U.S. parent. What do you think is the rationale for these regulations?
|
Compute the design factored load
: Compute the design factored load (wu) for the slab and (qu) for a typical beam.
|
Discuss the different c++ loops and their characteristics
: Discuss the different C++ loops, their characteristics
|
Do you agree with swobodas interpretation
: An Interpretation, Princeton Essays in International Finance 64, International Finance Section, Department of Economics, Princeton University, February 1968.) Do you agree with Swoboda's interpretation?
|
Carrot had current year taxable income
: Carrot Company has been profitable in the past and expects to remain profitable in the future. Carrot sells a product for which it provides a five year warranty.
|
Drilling fluids-volumes-tripping jobs
: Drilling fluid plays an important role in any drilling activity. It is the main controlling parameter in well control. Its main function is to control the bottom hole pressure (BHP) and stabilize the borehole. Therefore, it is very important to..
|