Question - A CCTV project for a company commenced on January 2018 and was expected to be complete by December 2018. A review done in October 2018 revealed the following information.
Budgeted Cost for Work Scheduled 1,500,000
Budgeted Cost for Work Performed 1,400,000
Actual Cost for Work Performed 1,600,000
Budgeted Cost for Total Work 2,000,000
Additional Cost for Completion 1,200,000
Required - Compute the Cost Variance (CV), Cost Performance Index (CPI) and the Estimated Cost Performance Index (ECPI) for the project.
Identify changes and improvement opportunities
: Summarise the supply chain associated with the work area or organisation - Summarise and analyse current performance to identify changes and improvement
|
How much did it actually cost john on an after-tax
: John Yee is an operations manager for a large manufacturer. He earned $68,000 in 2006. How much did it actually cost John on an after-tax
|
Continuous improvement and innovation review
: Discuss the current continuous improvement systems, processes, and innovations being used and What are the organisational requirements for approvals
|
Development important business strategy
: Why is employee training and development an important business strategy? How would you differentiate training and development?
|
Compute the cost variance and cost performance index
: Compute the Cost Variance (CV), Cost Performance Index (CPI) and the Estimated Cost Performance Index (ECPI) for the project
|
Determine the principal that will accumulate
: Determine the principal that will accumulate to $20,387.18 from March 12, 2017, to December 16, 2017, at 5% p.a. compounded semi-annually
|
Compute the operator hours that should be used
: The actual machine operator hours used were 0.30 per container. Compute the operator hours that should be used for the actual output of 9,900 containers
|
How much should hepburn record as amortization expense
: Hepburn Company bought a copyright for $90,000 on January 1, 2018, How much should Hepburn record as amortization expense
|
How many tickets do they need to sell over the season
: Adelaide United FC offers premium tickets for $40 and regular tickets for $30 for a match. How many tickets do they need to sell over the season
|