Construction Cost Estimate Assignment

A land developer plans to build a new building on a site that has marginal soil conditions. The geotechnical engineer has identified two alternative foundation systems for this proposed building:

Alternative 1: Support the building on pile foundations that extend through the marginal soils into the deeper stronger soils.

Alternative 2: Excavate the upper 10 feet of soil and replace it as a compacted fill. The proposed building may then be supported on spread footing foundations founded on the compacted fill.

Both alternatives will use a slab-on-grade floor. In addition, both alternatives will produce a foundation system with equal quality and reliability, and the construction time will be about the same. Neither will require any future maintenance. Thus, the only consideration in selecting the final design is the respective cost of the foundation construction.

The structural engineer developed preliminary design drawings for both alternatives, and these drawings show the following:

• The proposed building will be rectangular with plan dimensions of 150 ft by 200 ft. It will have 35 interior columns and all of the perimeter walls will be bearing walls.

• For Alternative 1, each column will require four piles, each of which must be 25 ft long. In addition, each column will require a 5x5x3 ft reinforced concrete pile cap. The exterior bearing walls will require 25 ft long piles at 10 ft on center, and a 2x2 ft reinforced grade beam along the base of the wall.

• For Alternative 2, each column will require a 10x10x3 ft reinforced concrete spread footing, and the exterior bearing walls will require a 3x2 ft reinforced concrete continuous spread footing.

The civil engineer developed a preliminary site plan and grading plan. For Alternative 2, the excavation and recompaction will extend 10 ft beyond the building footprint, as recommended by the geotechnical engineer. The civil engineer also determined that Alternative 2 will require 1800 cubic yards of import fill to make up for the shrinkage that will occur during the excavation and recompaction process.

Develop hand-drawn sketches of each alternative showing the relevant items needed to develop the cost estimate. Include relevant dimensions.

The unit cost information is as follows: Excavation and recompaction Materials $0

Equipment and labor $5.00 / yd3

Overhead and profit 10% of the materials, labor, and equipment costs

Import fill

Materials $20.00 / yd3

Equipment and labor $4.00 / yd3

Overhead and profit 10% of the materials, labor, and equipment costs

Pile foundations
Materials $27.00 / ft
Equipment and labor $9.50 / ft
Overhead and profit 10% of the materials, labor, and equipment costs

Reinforced concrete for pile caps and grade beams; includes excavation costs Materials $180.00 / yd3
Equipment and labor $230.00 / yd3
Overhead and profit 10% of the materials, labor, and equipment costs

Reinforced concrete for footings; includes excavation costs Materials $150.00 / yd3
Equipment and labor $200.00 / yd3
Overhead and profit 10% of the materials, labor, and equipment costs

Compute the construction quantity take offs and develop construction cost estimates for both alternatives.

Item

Quantity

Units

Materials

Equipment and Labor

Total Cost

Unit Cost

Cost

Unit Cost

Cost

Insulation R19

2000

sf

$0.20

$400

$0.18

$360

$760

Insulation R30

2300

sf

$0.28

$644

$0.20

$460

$1104

Drywall

4300

sf

$0.40

$1720

$0.62

$2666

$4386

Paint

4300

sf

$0.15

$645

$0.20

$860

$1505

Subtotal

 

 

 

 

 

 

$7755

10% overhead and profit

 

 

 

 

 

 

$775

Total

 

 

 

 

 

 

$8530

Based on the results of this analysis, recommend a course of action.

Your submittal should include:

• A cover sheet with the course name, the name of the assignment, your name, the submittal date, and any other information you deem to be relevant

• The hand-drawn sketches of each alternative

• Your quantity take offs and cost estimates presented as shown above with the relevant hand and/or spreadsheet calculations as needed.

• Short statement of your recommended course of action

Reference no: EM13912556

Questions Cloud

Calculate the total product costs incurred for the year : Calculate the total product costs incurred for the year. What is the product cost per unit?
Solve each given equation by factoring : Solve each equation by factoring or by using the Quadratic Formula-
Mass of the bike and rider : A bike coasts up a long hill. The hill has an incline of 38 degrees. The mass of the bike and rider is 129kg. If the bike starts up the hill at a velocity of 10 m/s, how far will the rider go up the hill before stopping? The coefficient of kinetic..
Compute the force exerted by the water : A swimming pool is 5m long, 4m wide and 3m deep. Compute the force exerted by the water against the bottom and either end. Do not include the force due to air pressure.
Compute the construction quantity take offs : Compute the construction quantity take offs and develop construction cost estimates for both alternatives.
Calculate cost of the september 30 work-in-process inventory : How do I calculate Cost of the September 30 Work-in-process inventory in the Weaving department? I am providing all of the information I have.
Spring constant of the bow : What is the spring constant of the bow? How much work does Sue do in pulling the arrow back? What is the speed of the arrow as it leaves the bow?
New automobiles : During the current year, Central Auto Rentals purchased 60 new automobiles at a cost of $21,920 per car. The cars will be sold to a wholesaler at an estimated $4,000 each as soon as they have been driven 56,000 miles
Find the total work done : A force F = - k ( x ˆ i + y ˆ j ) [where k is a positive constant] acts on a particle moving in the x-y plane.Starting from origin, the particle is taken to (a, a) and then to ( a 2 , 0. Find the total work done

Reviews

Write a Review

Civil Engineering Questions & Answers

  A new section of richmod highway is being designed

A new section of richmod highway is being designed as a six-lane facility (three in each direction) with a two-way, left-turn lane. Determine the peak hour LOS.

  Find entropy changes of refrigerant and thermal reservoir

A thermal reservoir (T=308K) is brought in contact with the tank, transferring enough heat to the tank to raise the pressure inside to 4 bar. Calculate the entropy changes of the refrigerant and the thermal reservoir

  Determine groundwater flow per unit width of the aquifer

The piezometer A is located 4,000 ft south of piezometer B.  Approximately 3,000 ft of piezometer B there is a river with an elevation relative to sea level of about 455 ft.

  What is the rate of water to be added to the tank

A hole at the bottom of a fish tank releases water at a rate given by the free jet equation. The hole at the bottom has a .5" diameter. If the water level is desired to be at 2' high and be at steady state, what is the rate of water to be added to th..

  On five-cycle semilogarithmic paper plot the grain size

on five-cycle semilogarithmic paper plot the grain size distribution curves from the following mechanical analysis data

  What is the probability that only one hurricane

If a year with occurrence of 2 events such as hurricane and tornado, 2 hurricanes, or 2 tornados is called a disaster year, what is the probability of a disaster year?

  What is the concentration of mlvss in the activated sludge

The concentration of Chemical Oxygen Demand (COD) in the effluent from this system is 25 mg L-1. The growth rate of the organisms in this case is 0.9 days-1. The activated sludge tank has a volume of 50 m3 and the flow rate through it is 500 m3 da..

  What is the percent decrease in the cross-sectional area

a circular aluminum tube of L=600 mm is loaded in compression by forces P. The outside and inside diameters are d2=75 mm and d1=63mm, respectively. A strain Gage is placed on the outside of the tube to measure normal strains in the longitudinal di..

  Determine the slederness ratio of a 5m column

determine the slederness ratio of a 5m column with built in ends if its cross section is circular with a radious of 40mm abd b 50mm square use the concept of effective length

  What is the maximum length to which it may be stretched

what is the maximum load that may be applied to a specimen with a cross sectional area of 130 mm^2 without plastic deformation.

  Compare prismoidal volume to the corrected end area volume

Calculate the prismoidal correction and compare the prismoidal volume to the corrected end area volume. Station Left Center Right Area (sq. ft.) 1+00 C7.0/ C8.2/ C8.5/ 256.90 31.3 0.0 24.5 1+50 C5.3/ C5.0/ C3.5/ 207.62 29.5 0.0 21.8 2+00

  Following results were obtained from direct shear tests

following results were obtained from direct shear tests on specimens of a sand compacted to the in-situ

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd