Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:
2020 2021
Costs incurred during the year $447,000 $1,110,000
Estimated costs to complete 1,043,000 0
Billings during the year 405,000 1,405,000
Cash collections during the year 305,000 1,505,000
Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.
Required:
Problem 1: Compute the amount of gross profit recognized during 2020 and 2021.