Question - Elf Builders Company entered into a P4.5M contract in early 2019 to construct a multipurpose hall for the city of Makati. Construction time is extended over the 2-year period. The table below describes the pattern of progress payments made by the City of Makati and costs incurred by Elf Builders by semiannual periods. Estimated costs of P3.6M were incurred as expected.
Progress Payments for Period
1/1/19 - 6/30/19 P750,000
7/1/19 - 12/31/19 P1,050,000
1/1/20 - 6/30/20 P1,950,000
7/1/20 - 12/31/20 P750,000
Progress Costs for Period
1/1/19 - 6/30/19 P900,000
7/1/19 - 12/31/19 P1,200,000
1/1/20 - 6/30/20 P1,080,000
7/1/20 - 12/31/20 P420,000
Elf Builders Company prepares financial statements twice each year, June 30 and December 31.
Required - Compute the amount of contract revenue, contract costs and profit for the four semiannual periods using the percentage of completion method.
Title vii of the civil rights act
: BFOQ's and "business necessity" sometimes serve as exceptions to the rule that you cannot discriminate in employment decisions.
|
What is the project profitability index
: It will generate positive cash inflows- Year 1 - $400,000; Year 2 - 500,000; Year 3 - $650,000; What is the project's Profitability Index
|
Strategies for managing conflict in dynamic world
: Using an organisation of your choice, discuss five (5) strategies for managing conflict in the dynamic world of today in order to achieve organisational goals i
|
Us participation and victory in wwii
: What changes (global, political, military leadership) resulted from US participation and victory in WWII?
|
Compute the amount of contract revenue
: Compute the amount of contract revenue, contract costs and profit for the four semiannual periods using the percentage of completion method
|
Attention to planning the effective use
: Senior managers spend considerable time planning for the efficient use of equipment, materials and money towards achieving their business objectives.
|
Outline an effective communications process
: Outline an effective communications process for a health care facility to enable smooth flow of information in the organization
|
Calculate the total goods available for sale for the period
: Using the information below, calculate the total goods available for sale for the period. Sales revenues for the period $1,304,000
|
Usability evaluation of an interactive system
: Usability Evaluation of an Interactive System - Define a set of usability requirements, considering what the design really needs to get right to achieve
|