Susan Cottenden clocked the observed time for welding a part onto truck doors at 5.3 minutes. The performance rating of the worker timed was estimated at 105%.

Find the normal time for this operation.

Note: According to the local union contract, each welder is allowed 3 minutes of personal time per hour and 2 minutes of fatigue time per hour. Further, there should be an average delay allowance of 1 minute per hour.

Compute the allowance factor and then find the standard time for the welding activity.

Reference no: EM131256215

Questions Cloud

Calculate the machining activity proportions for products : Atlanta Systems produces two different products, Product A, which sells for $253 per unit, and Product B, which sells for $413 per unit, using three different activities: Design, which uses Engineering Hours as an activity driver; Calculate the Desig..
Worked for the same company for three years : Julie is a fruit picker and has worked for the same company for three years. Between April and June 2005, she, along with 300 other fruit pickers, worked at this company. The workers, including Julie, worked an average of 40 hours per week, five d..
Impacted the performance evaluation : Explain how equal employment opportunity has impacted the performance evaluation and what employers need to be aware of.
Beginning inventory and ending inventory : Mendez Inc had the following information for the preceding year: Beginning Inventory (1/1) Ending Inventory (12/31) Work in Process Inventory $? $ 36,000 Finished Goods Inventory $ ? $ 33,500 Additional information for the year is as follows: Direct ..
Compute the allowance factor and then find the standard time : Find the normal time for this operation. - Compute the allowance factor and then find the standard time for the welding activity.
How many 800-n people could it carry : How many 800-N people could it carry? The blimp is filled with helium and standard conditions prevail. (This vehicle will not cause sea sickness and sunsets are spectacular!)
Consideration of the ideas and concepts : Your paper should demonstrate thoughtful consideration of the ideas and concepts that are presented in the course and provide new thoughts and insights relating directly to this topic. Your response should reflect scholarly writing and current APA..
Straight-line method and no salvage value : Listed below are the transactions of Newman Kawabata, D.D.S., for the month of September. Record depreciation using a 5-year life on the equipment, the straight-line method, and no salvage value. List of Accounts: Cash, Accounts Receivable, Rent Expe..
What is its density specific weight and specific gravity : An object is constructed of a material lighter than water. It weighs 50 N in air and a force of 10 N is required to hold it under water. What is its density, specific weight, and specific gravity?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd