Reference no: EM131241600
Part A -
Gino's Restaurant is a popular restaurant in Boston, Massachusetts. The owner of the restaurant has been trying to better understand costs at the restaurant and has hired a student intern to conduct an activity-based costing study. The intern, in consultation with the owner, identified the following major activities:
Activity Cost Pool
|
Activity Measure
|
Serving a party of diners
|
Number of parties served
|
Serving a diner
|
Number of diners served
|
Serving drinks
|
Number of drinks ordered
|
Some costs, such as the cost of cleaning the linens that cover the restaurant's tables, vary with the number of parties served. Other costs, such as washing plates and glasses, depends on the number of diners served or the number of drinks served.
Data concerning these activities are shown below.
|
Serving a Party
|
Serving a Dinner
|
Serving Drinks
|
Total
|
Total cost
|
$32,800
|
$211,200
|
$69,600
|
$313,600
|
Total activity
|
8,000 Parties
|
32,000 diners
|
58,000 drinks
|
|
Prior to the activity-based costing study, the owner knew very little about the costs of the restaurant. She knew that the total cost for the month was $313,600 and that 32,000 diners had been served. Therefore, the average cost per diner was $9.80 ($313,600 ÷ 32,000 diners = $9.80 per diner).
Required:
1. Compute the activity rates for each of the three activities.
2. According to the activity-based costing system, what is the total cost of serving each of the following parties of diners? (Do not round intermediate calculations. Round your final answers to 2 decimal places.)
a. A party of four diners who order three drinks in total.
b. A party of two diners who do not order any drinks.
c. A party of one diner who orders two drinks.
3. Convert the total costs you computed in part (1) above to costs per diner. In other words, what is the average cost per diner for serving each of the following parties? (Do not round intermediate calculations. Round your final answers to 2 decimal places.)
a. A party of four diners who order three drinks in total.
b. A party of two diners who do not order any drinks.
c. A party of one diner who orders two drinks.
Part B -
Marine, Inc., manufactures a product that is available in both a flexible and a rigid model. The company has made the rigid model for years; the flexible model was introduced several years ago to tap a new segment of the market. Since introduction of the flexible model, the company's profits have steadily declined, and management has become concerned about the accuracy of its costing system. Sales of the flexible model have been increasing rapidly.
Overhead is applied to products on the basis of direct labor-hours. At the beginning of the current year, management estimated that $600,000 in overhead costs would be incurred and the company would produce and sell 1,000 units of the flexible model and 10,000 units of the rigid model. The flexible model requires 2.0 hours of direct labor time per unit, and the rigid model requires 1.0 hours. Direct materials and labor costs per unit are given below:
|
Flexible
|
Rigid
|
Direct materials cost per unit
|
$110.00
|
$80.00
|
Direct labor cost per unit
|
$30.00
|
$15.00
|
Required:
1. Compute the predetermined overhead rate using direct labor-hours as the basis for allocating overhead costs to products.
2. An intern suggested that the company use activity-based costing to cost its products. A team was formed to investigate this idea. It came back with the recommendation that four activity cost pools be used. These cost pools and their associated activities are listed as follows:
|
|
Expected Activity
|
Activity Cost Pool and Activity Measure
|
Estimated Overhead Cost
|
Flexible
|
Rigid
|
Total
|
Purchase orders (number of orders)
|
$20,000
|
100
|
300
|
400
|
Rework requests (number of requests)
|
10,000
|
60
|
140
|
200
|
Product testing (number of tests)
|
210,000
|
900
|
1,200
|
2,100
|
Machine related (machine-hours)
|
360,000
|
1,500
|
2,500
|
4,000
|
|
$600,000
|
|
|
|
Compute the activity rate for each of the activity cost pools.
3. Using activity-based costing, do the following:
a. Determine the total amount of overhead that would be assigned to each model for the year.
b. Compute the unit product cost for one unit of each model.
Are existing capital structures necessarily optimal
: Are existing capital structures necessarily optimal? - How can managers reduce the likelihood that they will run out of cash? - How does a coercive bond exchange offer work?
|
What is a good predictor for future ipo waves
: What are the main empirical regularities about IPO pricing and stock returns? - What is a good predictor for future IPO waves.
|
Focuses on ends of development
: Recall that the HDI focuses on "ends of development" like longevity, knowledge and material choice income), rather than on the "means" what has been the case of GNP. What are some of the main criticisms of against the use of GDP per capita as a measu..
|
What strategies can parents of adolescent children use
: What strategies can parents of adolescent children use to prevent or end troublesome behavior and maintain a positive family environment? Do family structure, dynamics, and culture play a role in maintaining such an environment?
|
Compute the activity rates for each of the three activities
: Compute the activity rates for each of the three activities. According to the activity-based costing system, what is the total cost of serving each of the following parties of diners? (Do not round intermediate calculations. Round your final answer..
|
Find the steady-state expression
: ]Use the mesh-current method to find the steady-state expression - Express the voltage in both polar and rectangular form and Use the mesh-current method to find the steady-state expression for vo(t) in the circuit.
|
How large will the new output alphabet be
: In general, for any input alphabet A and output alphabet B, with |B| = k, if we take a new input alphabet A⊂ A, how many elements will the new output alphabet have? What will the new output alphabet be?
|
Is average private value equal to expected painting value
: Is the average private value equal to the expected painting value? - What should be your absolute maximum bid before you expect to lose money?
|
Describe elements of conflict resolution and peacemaking
: Locate an article concerning conflict resolution and peacemaking using the course readings, the University Library, and other resources. Prepare a 900-word paper in which you analyze your article. Describe elements of conflict resolution and peacema..
|