Reference no: EM131939856
Question: Assume that Wal-Mart Stores, Inc. has decided to surface and maintain for 10 years a vacant lot next to one of its stores to serve as a parking lot for customers. Management is considering the following bids involving two different qualities of surfacing for a parking area of 12,400 square yards.
Bid A: A surface that costs $5.25 per square yard to install. This surface will have to be replaced at the end of 5 years. The annual maintenance cost on this surface is estimated at 25 cents per square yard for each year except the last year of its service. The replacement surface will be similar to the initial surface.
Bid B: A surface that costs $9.75 per square yard to install. This surface has a probable useful life of 10 years and will require annual maintenance in each year except the last year, at an estimated cost of 10 cents per square yard.
Compute present value of the bids. You may assume that the cost of capital is 10%, that the annual maintenance expenditures are incurred at the end of each year, and that prices are not expected to change during the next 10 years. (Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 458,581.)
Present value of outflows for Bid A $
Present value of outflows for Bid B $
Which bid should be accepted by Wal-Mart.
Wal-Mart should accept
Bid ABid B
Compute how much money will you have in the account
: How much money will you have in the account 15years later at age 55 if the account continues to earn 9.5% per year but you discounted making new contributions.
|
The capital market is perfect
: CoinBase will generate a cash flow of $220M or $80M if next year the economy is in boom or recession respectively. The capital market is perfect.
|
What is the current two-year treasury yield
: Assume the unbiased expectations theory is true. The current, 1-year Treasury yield is 4%. Suppose the market expects that the 1-year Treasury yield.
|
Calculate the dirty price of the bond
: The ask yield is 7 percent. Calculate the dirty price of the bond.
|
Compute present value of the bids
: Compute present value of the bids. You may assume that the cost of capital is 10%, that the annual maintenance expenditures are incurred.
|
What would the new grm be
: If the investor were planning to make improvements in the amount of $500,000, which should result in an increase in gross scheduled income in the amount.
|
Relationship between the coupon rate and discount rate
: Show that your results are consistent with the relationship between the coupon rate, discount rate, and price relative to par value.
|
Indicate the effect of the preceding information
: Indicate the effect on the balance sheet and income statement of the preceding information for 2009, 2010, and 2011 under each of the following valuation method
|
What should be the price of par-value bond
: Assuming the market is arbitrage-free, if a six-month pure discount bond yields 1.9%, a one-year pure discount bond yields 2.3%.
|