Compute overall system reliability under plan

Assignment Help Operation Management
Reference no: EM131426800

A production line has three machines A, B, and C, with reliabilities of .97, .87, and .88, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineers are weighing two alternative designs for increasing the line’s reliability. Plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. In either case, three machines (A, B, and C) would be used with reliabilities equal to the original three.

a. Compute overall system reliability under Plan 1. (Round your intermediate calculations and final answer to 4 decimal places.

Reliability ____    

b. Compute overall system reliability under Plan 2. (Round your intermediate calculations and final answer to 4 decimal places.)

Reliability ____    

c. Which plan will provide the higher reliability?

Plan2

Plan1

Reference no: EM131426800

Questions Cloud

Discussion of job range-job depth and job relationships : Review the text discussion of Job Range, Job Depth, and Job Relationships. Using the terms used in the text and in at least ONE other reference on this topic, describe your current job position or one with which you are familiar. Be sure to describe ..
Expected number of toys needed until you have a complete set : Assume that each time you collect a toy, it is equally likely to be any of the n types. What is the expected number of toys needed until you have a complete set?
Assess the challenge of managers providing accurate feedback : Assess the challenges of managers providing accurate, timely, and effective feedback to employees. Recommend how managers can overcome any two of the challenges you identified.
Efficiency wage theory : Argue persuasively and critically why paying a higher wage rate based on Efficiency Wage Theory can be effective in raising up productivity, workplace cohesiveness, employee responsiblililty and loyalty and reduces shirking.
Compute overall system reliability under plan : A production line has three machines A, B, and C, with reliabilities of .97, .87, and .88, respectively. The machines are arranged so that if one breaks down, the others must shut down. Compute overall system reliability under Plan 1.
How can the forecasts be improved : Collect a reasonably long set of data, and see how well standard forecasting methods work. How can the forecasts be improved?
Consider a pure exchange economy with wine : Consider a pure exchange economy with wine (x) a cheese (y) only and two consumers only. Let cheese is numeraire good with price of $1. For each of the following set of consumers,
Probability that another one would not occur : If a test occurred at 6:00 a.m., what is the probability that another one would occur before 6:00 p.m.?- If a test occurred at 10:00 p.m., what is the probability that another one would not occur until after 6:00 a.m.?
Description of the industry : In a paragraph or less, provide a brief description of the industry that you have selected to include at least the following:

Reviews

Write a Review

Operation Management Questions & Answers

  Discuss about the marketing strategy analysis

Your project must be a minimum of 20 pages, not including cover page, abstract, table of contents, references, and any appendices.Project includes at least five references, used and cited within, in APA format.Ensure that any graphics you have are ..

  Scope of his employment in each of these situations

John drives a truck as an employee for Quik Delivery, Inc. Would John be acting outside the scope of his employment in each of these situations?

  A producer of inkjet printers is planning to add a new line

a producer of inkjet printers is planning to add a new line of printers and you have been asked to balance the process

  Capital investment financial analysis involves

A capital investment financial analysis involves which of the following steps?

  How did the corporation perform the past year overall

how did the corporation perform the past year overall in terms of return on investment, market share, and profitability?

  Technology has enabled them to increase productivity

The Dulac Box plant works two 8-hour shifts each day. In the past, 500 cypress packing boxes were produced by the end of each day. The use of new technology has enabled them to increase productivity by 30%. Productivity is now approximately

  Channels of distribution that employ sales professionals

Our textbook discusses three channels of distribution that employ sales professionals. Discuss the main components of the Business-To-Business Channels. Which career opportunity within this channel do you see yourself working in? Explain why you chos..

  What are the ethical implications of requiring

What are the ethical implications of requiring that employees dedicate long hours and extensive travel time to their careers.

  Provide three examples of foreign firms

Provide three examples of foreign firms that have invested in the U.S. Discuss why these companies invested in the U.S. Follow the framework presented in the text. Explore what the investment means for the U.S.

  Firm multifactor productivity before and after changes

What is the firm's multifactor productivity before and after the changes? Why is it important to be aware of the productivity changes?

  Define global supply chain management strategy

There are a number of companies that utilize a global supply chain management strategy. Identify and research a company with a successful global supply chain management strategy and provide basic background information. Discuss the strategies this..

  Company opts to use acceptance testing

If a company opts to use acceptance testing, it's producer's risk would be:

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd