Compute activity slack and identify the critical path

Assignment Help Operation Management
Reference no: EM131701939

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? How many paths are in this project? If the original schedule for this project was 15 days, will it complete on time, or early or late?

ID        Description                                           Predecessor                      Duration

A          Survey site                                            None                                    2

B          Install drainage                                    A                                            5

C          Install power lines                              A                                            3

D          Excavate site                                        B, C                                       5

E          Pour foundation                                 D                                            4

Reference no: EM131701939

Questions Cloud

What are advantages and disadvantages of this measure : What are the advantages and disadvantages of this measure? Are there any alternate courses of action that would give the same end results?
Skillful negotiators : American negotiators will know when to ______ and Indian negotiators look for and say the _____. The ______ are skillful negotiators.
Contributed to the formation of new racial caste system : What do you think of Alexander's argument that the law has contributed to the formation of a new racial caste system?
Ethical issues arise in the workplace all the time : Ethical issues arise in the workplace all the time.
Compute activity slack and identify the critical path : Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
Walk-ins usually have a good basic skill set : One of the strengths of public agencies is that they heavily prescreen recruits. Walk-ins usually have a good basic skill set.
Case study-skullcandy : Was the headphone an attractive industry when Alden entered with Skullcandy? How are Skullcandy’s products positioned?
Discuss how cell phone manufacturers can use : Discuss how cell phone manufacturers can use: product differentiation, capacity control to manage rivalry and increase the industry's profitability.
The use of intelligence-led policing : The use of intelligence-led policing I in law enforcement is viewed by some as limited to intelligence activities,

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd