Compute a predetermined overhead rate for the plant

Assignment Help Accounting Basics
Reference no: EM132743731

Question: Cekap Sdn Bhd has two departments and currently is using a plantwide overhead rate based on machine hours in allocating overhead costs to each department. The plant manager has been briefed that the departmental overhead rates offer substantially better cost assignments than a plantwide rate does. Cekap has the following data for its two departments for the coming period:

Department A

Overhead costs (estimated) RM37,500

Machine hours (estimated) 5,000

Department B

Overhead costs (estimated) RM16,500

Machine hours (estimated) 4,000

1) Which costing system is used by Cekap Sdn Bhd (normal vs actual)? Explain.

2) Compute a predetermined overhead rate for the plant as a whole based on machine hours.

3) Compute predetermined overhead rates for each department using machine hours (Note: Format your calculations out to three decimal places).

4) Job C11 used 10 machine hours from Department A and 25 machine hours from Department B. Job C12 used 25 machine hours from Department A and 10 machine hours from Department B.

a) Compute the overhead cost assigned to each job using the plantwide rate computed in (2).

b) Repeat the computation using the departmental rates found in (3).

c) Which of the two approaches gives the fairer cost assignment? Why?

5) What If Analysis: Repeat Requirement (4), assuming the expected overhead cost for Department B is RM30,000 (not RM16,500). For this company, would you recommend departmental rates over a plantwide rate? Briefly explain.

Reference no: EM132743731

Questions Cloud

What is the markup percentage using total cost per unit : Schopp Corporation makes a mechanical stuffed alligator that sings the Martian national anthem. The following information is available for Schopp Corporation's.
Find how much will pay for the property : Find How much will you pay for the property if you believe its market risk is the same as the market portfolio's? The T-bill rate is 4%, and the expected
Explain bond equivalent yield : What would be your bond equivalent yield if you sold the bond for current market price of ?$1,052??
What are the project costs of capital for new ventures : The Treasury bill rate is 4%, What are the project costs of capital for new ventures with betas of 0.85 and 1.78? (Do not round intermediate calculations.)
Compute a predetermined overhead rate for the plant : Cekap Sdn Bhd has two departments and currently is using a plantwide overhead rate based on machine hours in allocating overhead costs to each department.
Write the reasons for allocation : You can assume more as you need. Write the reasons for your allocation.
Explain what is the required rate of return on the project : Explain What is the required rate of return on the project if its beta is 1.80? (Do not round intermediate calculations. Enter your answer as a whole percent.)
What is cost of common equity : Using the discounted cas flow approach (Gordon model), what is its cost of common equity?
What is the present value of the lease payments : If the discount rate is 14%, what's the present value of the lease payments? The response must be typed, double spaced, times new roman, font size 12.

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd