Computation of approximate cost of the cash float per day

Assignment Help Finance Basics
Reference no: EM1312587

Computation of approximate cost of the cash float per day.

Your firm has average daily receipts of $2,500. These receipts are available after 6 days on average. The interest rate that could be earned is .02% (.0002) per day. What is the approximate cost of the float per day?

Reference no: EM1312587

Questions Cloud

Computation of the interest on the loan payable in due : Computation of the interest on the loan payable in due and in advance and What will be the face value of the note assuming that Interest paid when the loan is due
Computation of the future contracts and the margin money : Computation of the future contracts and the margin money and how much money will be required for margin account
Probability by quantum tunneling : Keeping a constant speed of 0.6 m/s, a marble of mass 18 g rolls back & forth across a shoebox that is 14 cm high & 2 mm thick. Estimate the probability of its escaping through the wall of the box by quantum tunnelling.
Discuss on collectability of the accounts receivables : Discuss on collectability of the accounts receivables and Collegiate wants to stem their losses by using an instant electronic credit check on the customer
Computation of approximate cost of the cash float per day : Computation of approximate cost of the cash float per day and the interest rate that could be earned is .02% .0002 per day
Transmission coefficient of an electron : Classically, the electron cannot pass through the barrier because E
Computation of optimum cash balance and savings : Computation of optimum cash balance and savings there on using Baumol model and What is the total saving to the firm if it switches from its current practice to the optimum practice
Find distance travelled by the block on an inclined plane : Block A of Figure has a velocity of 15 ft/sec down slope. How far will the block slide along the slope? How far will the block slide along the slope before stopping?
Computation of the effective interest rate on the bank loan : Computation of the effective interest rate on the bank loan and compensating balance requirement which is based on the total amount borrowed

Reviews

Write a Review

Finance Basics Questions & Answers

  Computation of first three years schedule of loan

Computation of first three years schedule of loan and the requires that Dagnay pay off the loan over a twenty-year period

  Performing dupont analysis on project

Is this project in division manager’s best interests? Explain why or why not? Carry out DuPont Analysis on this project. Determine the project’s residual income?

  Determining best evaluation of company-s cost of equity

If stock sells for $39 per share, Determine your best evaluate of company’s cost of equity? Answer in a %.

  Compute of after-tax profit

Compute of after-tax profit and The corporate tax rate is 40%. If the economy is strong the firm will sell 2,000,000 gadgets

  Procedure of loan amortization also capital recovery

Illustrate procedure of loan amortization also capital recovery through suitable example.

  Health administration requires the firm to install equipment

The Occupational Safety as well as Health Administration requires the firm to install new ventilating equipment in its plant, Theory Question regarding specific factors affecting firm's breakeven point

  Forecasted interest expense on balance of debt

Suppose that all extra debt in the form of the line of credit is added at the ending of year that means that you must base forecasted interest expense on balance of debt at the commencement of year.

  Compute the market value

Compute the market value and What is the maximum amount that can be loaned on a property whose net operating income

  Financial reporting and analysis

Finance is about Gunns Ltd, a company in dealing with forestry products in Australia. The company has also been listed in Australian Stock Exchange. As many companies producing forestry products, even Gunns Ltd is facing various problems. Due to the ..

  Compute the present value of a two-period annuity

Q. Compute the present value of a two-period annuity of $1 per period if the discount rate is 10 percent,  A two-period annuity of $1 per period has a present value of $1.808.  Find the discount rate from the present value table.

  Wellpoint and anthem merger

Describe the transaction structure, mode of payment, and financing.

  Computation of after tax rate of return on investment

Computation of after tax rate of return on investment Assume that federal taxes are not deductible against state taxes and vice versa

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd