Complete the network diagram by conducting a forward

Assignment Help Project Management
Reference no: EM13881769

Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity

2.  What is the project duration?

3.  What is the critical path of this network?

4.  Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E).  Assume only one Carpenter is available and two Electricians are available. 

5.  Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project.  Illustrate this new resource constrained network in a network diagram.

6.  Complete the resource activity schedule.

7.  For the new network, what is the new project duration?

8.  Which activities are now critical? 

 

 

Reference no: EM13881769

Questions Cloud

Demographic trends in different areas of the country : Discuss the impact of each of the following on prepayment risk for a mortgage backed pass through security (MBS): a. High coupon interest MBS versus low coupon interest MBS b. MBS issued six years prior versus MBS issued this year c. Demographic tren..
Provides essential information to assess a given project : When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project.
Estimate the adiabatic flame temperature of cyclopentane : Suppose you discover after the combustion has been carried out that the thermocouple is not functioning properly. Use the final pressure gauge reading of 75.3bar to estimate the adiabatic flame temperature of cyclopentane. Do not assume ideal gas ..
Discuss the accounting treatment of the depletion calculated : 1.On April 17, 2013, the Loadstone Mining Company purchased the rights to a coal mine.
Complete the network diagram by conducting a forward : Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity 2.  What is the project duration?
Is there evidence of multicollinearity in the data : Regress average hours worked during the year on the variables given in the table and interpret your regression.
What court are you in and how did you get there : What court are you in and how did you get there? (almost all of the cases we discuss are decided by an appeals court, but were initially heard at a trial level court - explain that path for your case)
The value of money changes over time : The value of money changes over time. Discuss the principles of capital budgeting and how the outcome of this analysis can influence the "go - no go" decision
What is the total amount of interest paid : What is the amount of each payment? What is the total amount of interest paid? How does the total interest paid compare with the principal of the loan?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd