Assignment - Building a Tiny Home

Determine Budget/Time-Phased Cash Flow

The Case:

The City of Peterborough has decided to try something new to address the significant issue of homelessness. The city council is interested in pursuing a community of tiny homes, with most of the features of a full-sized home, to allow an affordable housing option for those on limited incomes. The first step in the project is to construct a single home to verify the costs and timeline projected for the effort.

You have been selected as the project manager for the initial tiny home. Your company has a good reputation for quality work and the ability to manage issues effectively. The total budget for the effort is $40,000 CAD, and you have been given one month to complete the work. You will be responsible for having all of the work completed, as well as keeping track of the cash flow on the project to serve as a guideline for future builds. The house will be built on an unused piece of city property, for transportation to its final location later. You will allow for a 10% budget contingency on all tasks to account for any possible risks on the project. It is also customary that no work will take place on the weekends. Your time as a project manager will be calculated at 30% of the numbers of hours for each whole day of the project.

Your Mission:
1. Complete the basis of estimates and budget worksheet using the task and resources information in this case.
2. Complete a time-phased cash flow forecast on the associated worksheet.
3. Answer the questions at the bottom of the "Budget" worksheet

Project Data
Human Resources

Resource

$ per Hr

% of time allocated per task

Project Manager

100

30

General Labour

25

100

Framer

30

100

Electrician

40

100

Plumber

40

100

Roofer

25

100

Assumptions:
1 day = 8 hrs
*Task durations will be rounded to nearest whole day

Project Tasks:
1. Buy a tiny house trailer and level it on the property.
a. Trailer - $2500
b. General Labour - Optimistic hrs (6), Most Likely Hrs (8), Pessimistic hrs (10)
2. Build and insulate the foundation and install the subflooring.
a. Material - $1000
b. Framers - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is Task 1
3. Frame and install the wall sections including the lofts for sleeping.
a. Materials - $2500
b. Framers - Optimistic hrs (28), Most Likely Hrs (32), Pessimistic hrs (36)
c. Predecessor is task 2
4. Install the roof rafters and sheathing.
a. Materials $1000
b. Framers - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 3
5. Enclose the house with sheathing and ty-par weather resistant wrap.
a. Materials $1000
b. General Labour - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 4
6. Install windows and doors.
a. Materials $1000
b. General Labour - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 5
7. Install the roof.
a. Materials $2000

b. Roofers - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 5
8. Install exterior siding and trims.
a. Materials $2000
b. General Labour - Optimistic hrs (20), Most Likely Hrs (23), Pessimistic hrs (30)
c. Predecessor is tasks 6,7
9. Plumbing rough-in
a. Materials $2000
b. Plumber - Optimistic hrs (20), Most Likely Hrs (23), Pessimistic hrs (30)
c. Predecessor is task 7
10. Electrical rough-in
a. Materials $2000
b. Electrician - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 9
11. Insulate the walls and roof.
a. Materials $1000
b. General Labour - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 10
12. Install interior siding and trims.
a. Materials $1500
b. General Labour - Optimistic hrs (14), Most Likely Hrs (15), Pessimistic hrs (20)
c. Predecessor is task 11
13. Finishing touches
a. Materials $500
b. General Labour - Optimistic hrs (6), Most Likely Hrs (8), Pessimistic hrs (10)
c. Predecessor is task 12

City of Peterborough Schedule of Payments Week 1 - $8000
Week 2 - $8000 Week 3 - $9000 Week 4 - $15,000

Attachment:- Time-Phased Cash Flow.rar

Reference no: EM133346348

Questions Cloud

Complete the discovery wheel assessment : Complete the discovery wheel assessment, journal entry 23, and provide a list of those scores. Then in a journal format write a 3 paragraph reflection by answer
What is the societal implication of delusion : what is the societal implication of delusion? I am working on a project exploring the boundaries between delusion and reality.
What is the difference in expected monetary cost between : What is the difference in expected monetary cost between paying the meter for two hours and risking a ticket? Use a positive figure
What is the difference in expected time between taking : What is the difference in expected time between taking the expressway and taking the side roads? Give an answer as a positive value in hours
Complete the basis of estimates and budget worksheet : Complete the basis of estimates and budget worksheet using the task and resources information in this case and Complete a time-phased cash flow forecast
Explain this conclusion given the argument discussed : Explain this conclusion given the argument discussed in class. Why is it that many people hold the intuition that our minds would indeed be uploaded
What is there a moral obligation to others in need : "Is there a moral obligation to others in need?" Be sure that your answer offers the reasoning for your conclusion along with any details regarding the nature
How often do you believe we morally judge people for events : what extent do you believe our assessment of other people's moral character is a matter of luck ? That is to say, how often do you believe we morally judge
Discuss and evaluate locke arguments against innate ideas : This is reminiscent of the 'nature/nurture' controversy we discussed at the beginning of the semester. Critically discuss and evaluate Locke's arguments against

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd