A new highway is to be constructed. Design A calls for a concrete pavement costing $85 per foot with a 16?-year ?life; three paved ditches costing $3 per foot? each; and four box culverts every? mile, each costing $9,000 and having a 16?-year life. Annual maintenance will cost $1,600 per? mile; the culverts must be cleaned every four years at a cost of $400 each per mile.

Design B calls for a bituminous pavement costing $45 per foot with a 8?-year ?life; three sodded ditches costing $1.30 per foot? each; and four pipe culverts every? mile, each costing $2,300 and having a 8?-year life. The replacement culverts will cost $2,450 each. Annual maintenance will cost $2,800 per? mile; the culverts must be cleaned yearly at a cost of $ 220 each per? mile; and the annual ditch maintenance will cost ?$1.30 per foot per ditch.

Compare the two designs on the basis of equivalent worth per mile for a 16?-year period. Find the most economical design on the basis of AW and PW if the MARR is 12% per year.

Reference no: EM131997945

Questions Cloud

Reason technical analysis might be profitable : What is not a reason technical analysis might be profitable?
What is the aftertax cost of debt : What is the company’s WACC? What is the aftertax cost of debt?
What is percentage change in the price of bond : If interest rates suddenly rise by 2 percent, what is the percentage change in the price of Bond Sam and Bond Dave?
Determine the costs of the process and the net benefits : Identifying a process improvement opportunity. Create a formula to calculate the benefits. Determine the costs of the process and the net benefits.
Compare the two designs on the basis of equivalent worth : Compare the two designs on the basis of equivalent worth per mile for a 16?-year period. Find the most economical design on the basis of AW and PW
Bond outstanding with annual interest payment : Preston Corporation has a bond outstanding with an annual interest payment of $100, a market price of $1,300, and a maturity date in 6 years.
What is the remaining ucc after year six : What is the remaining UCC after Year 6? Assume a tax rate of 40 percent.
Compute the current yield on both bonds : Bond X pays $78 annual interest and has a market value of $850. It has 13 years to maturity. Compute the current yield on both bonds.
Find market value of the bonds using semiannual analysis : Find the market value of the bonds using semiannual analysis.

Reviews

Write a Review

Financial Management Questions & Answers

  How much money does she currently have saved

Kristina started setting aside funds three years ago to save for a down payment on a house. How much money does she currently have saved?

  Monetary policy conducted by the federal reserve

What are the primary goals of the monetary policy conducted by the Federal Reserve?

  Expected rate of return from this investment opportunity

James Fromholtz is considering whether to invest in a newly formed investment fund. The fund’s investment objective is to acquire home mortgage securities at what it hopes will be bargain prices. The fund sponsor has suggested to James that the fund’..

  If a shareholder works for the business

If a shareholder works for the business then he:

  Challenge to capital budgeting strategies

A Challenge to Capital Budgeting Strategies Financing corporate purchases and overall capital budgeting usually requires the finance manager to assess tax rates

  Private firm in the holiday gift industry

Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project.

  Determine the value of a share of dupont series

Determine the value of a share of DuPont Series A $4.50 cumulative preferred stock, no par, to an investor who requires a 9 percent rate of return on this security.

  The expansion requires immediate outflow

S. Miller is looking to expand an existing project. The expansion requires an immediate outflow (an investment today) of $77 million. S. Miller anticipates that the project will generate one future cash flow of $195 million that will arrive at the en..

  What is the cost of preferred equity

what is the cost of preferred equity if there are no flotation costs?

  How many shares of stock must you buy to establish

If you are short one call option with strike price 83 and maturity of 8 months, how many shares of stock must you buy to establish a delta-neutral position?

  Materials-handling machine for its manufacturing operations

Carson Electronics is currently considering whether to ac-quire a new materials-handling machine for its manufacturing operations.

  How much is share of stock worth today

If the appropriate discount rate is 10%, then how much is a share of Cliff Corp. stock worth today?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd