The XYZ compact company uses  a job costing system. The company estimated its annual overhead to be $100,000 and the number of direct labor hours for the year to be 20,000 hours.  In the first month, the following jobs were completed:
Job#115	Job #205
direct materials used	$11,000	$14,500
direct labor cost	$23,000	$12,500
direct labor cost	1,500 hours	1,250 hours
a. What is the company's predetermined overhead rate using direct labor hours as a base?
b. What is the overhead assigned to job#115?
c. What is the overhead assigned to job #205?
d. What is the total manufacturing cost for job #115?
e. What is the total manufacturing cost for job #205?