Clay was extracted from a soil sampling tube to form

Assignment Help Civil Engineering
Reference no: EM13546715

Clay was extracted from a soil sampling tube to form a cylindrical sample 100 mm in diameter and 100mm in length.the sample was weighed in its natrual moist state and found to have a total mass of 1531g. After drying, the sample was weighed again and the dry mass was found to be 1178g.

If the specfic gravity of the soil particles is 2.75,calculate the following properties of the clay:

a) Bulk density

b) Water content

c) void ratio

d) Dry density

e) Degree of saturation

f) Air void content

Reference no: EM13546715

Questions Cloud

Prove clausius inequality in steam power plant operating : Prove clausius inequality in steam power plant operating in cycle.given that heat transfer in boiler =2070kJ/kg at 164 degree celcius ;heat tranfer in condenser =1905 kJ/kgat 52 degree celcius.
Bad debt expense for the year balance : Bad debt expense for the year balance in the allowance account after the adjustment of Dec 31
What would be the indifferent point : What would be the indifferent point?
Discuss the capital budgeting process : Discuss the capital budgeting process and the inputs that are used in capital budgeting.
Clay was extracted from a soil sampling tube to form : Clay was extracted from a soil sampling tube to form a cylindrical sample 100 mm in diameter and 100mm in length.the sample was weighed in its natrual moist state and found to have a total mass of 1531g
Prepare companys journal entry to record the notes issuance : Prepare the company's journal entry to record the note's issuance, prepare the journal entries for the first and second installment payments
Prepare a report for the firm ceo indicating : Prepare a report for the firm's CEO indicating which projects should be accepted and why
How does it impacts the accounting equation : How does it impacts the accounting equation. Make sure to identify the two accounts impacted. Why is it important to record your selected transaction?
Determine the expected net realizable value : Determine the expected net realizable value of the accounts receivable as of Dec 31 and journalized the adjusting entry.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Determine flow on the road and space mean speed

Data obtained from aerial photography showed six vehicles on a 600 ft long section of road. Traffic data collected at the same time indicated an average time headway of 3.6 sec.

  Calculate strains for case where coordinate axes are rotated

An element of material subjected to a plane strain has a strain epsilon x of 280x10^-6, a strain epsilon y of 420x10^-6 and an engineering shear strain gamma xy of 150x10^-6.

  Estimate amount leached from concrete during one-year period

Estimate the amount of Ca(OH)2(s) leached from concrete during a one-year period by precipitation. Assume that the area receives 40 in/yr of precipitation which is in equilibrium with PCO2= 10^-3.5 atm and [SO42-] = 10^-4 M.

  Calculate the axial and radial strains and volumetric strain

A cylindrical soil, 75mm in diameter and 150 mm long, is radially compressed. The length increases to 153 mm and the radius decreases to 37.2 mm. Calculate: a) The axial and radial strains b) The volumetric strains

  Determine return period of the intensity using annual series

All but 5 of the 60 years experienced one or more 30-min intensities equaling or exceeding the 2.5 in/hr value. Use the Kimball formula to determine the return period of this intensity using

  Explain important information about short essay

Important information about Short essay, In managing the uncertainties of ethical issues in engineering, what are some questions that we may ask to limit some of the risk

  What is the total change in energy of the hammerhead

a piston moves a 25kg hammerhead vertically down 1m from rest to a velocity of 50m/s in a stamping machine. what is the total change in energy of the hammerhead

  Determine the resultant moment produced by the load

The tower crane is used to hoist the 2-Mg load upward at constant velocity. The 1.5-Mg jib BD , 0.5-Mg jib BC , and 6-Mg counterweight C have centers of mass at G1 , G2 , and G3 , respectively.

  What is the biomass concentration in the aeration tank

average flow rate = .0022 m^3 /s (190 m^3 /d) Influent Substrate concentration = 250 mg/L as COD (all essentially soluble) Mean cell residence time is to be 5 days Volume of mix tank = 25 m^3 the reactors kenetic constants are

  Which option should to select to maximize the payout

You are the winner of a sweepstakes and given a choice of a one-time payment of $1,000,000 or a guaranteed $80,000 per year for 20 years. Assume that you will collect all 20 years regardless of health condition.

  Calculate the pressure in psignat the bottom of the tank

Assume a hydrostatic condition in a cubic tank with 64ft length, 32ft width and 16ft height. The tank is filled with 15ppg( pounds per gallon) fluid. Calculate the pressure in psignat the bottom of the tank.

  Compare the total reactor volume required for removal

Compare the total reactor volume required for 90% removal of a substance that decays according to first-order kinetics with a rate constant of 0.05 day -1 in a CM system that contains a single reactor against a system that contains three CM reacto..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd