Reference no: EM131065210
JOHNSTON PRODUCTS
No matter how many times Justin Wang, the master scheduler for Johnston Products, tried, he couldn't seem to get it through people's minds. They kept trying to "front load" the production schedule, and the problem appeared to be getting worse.
By "front loading" Justin meant that production supervisors would attempt to catch up with production they failed to make the previous week. It seemed to happen every week, and the only way Justin could get things back to a realistic position was to completely reconstruct the entire master schedule-usually about every three weeks.
Last month could serve as an example. The first week of the month Justin had scheduled production equal to 320 standard hours in the assembly area. The assembly area managed to complete only 291 hours that week because of some equipment maintenance and a few unexpected part shortages. The assembly supervisor then had the workers complete the remaining 29 hours from week 1 at the start of week 2. Since week 2 already had 330 standard hours scheduled, the additional 29 hours really put them in a position of attempting to complete 359 hours. The workers actually completed 302 hours in week 2, leaving 57 hours to front load into week 3, and so forth. Usually by the time Justin came to his three-week review of the master schedule, it was not uncommon for the assembly area to be more than 100 standard hours behind schedule.
Clearly something needed to be done. Justin decided to review some of the areas that could be causing the problem:
1. Job standards-Although it had been at least four years since any job standards had been reviewed or changed, Jason felt the standards could not be the problem- quite the opposite. His operations course had taught him about the concept of the learning curve, implying that if anything the standards should be too large, allowing the average worker to complete even more production than implied by the job standard.
2. Utilization-The general manager was very insistent on high utilization of the area. He felt that it would help control costs, and consequently used utilization as a major performance measure for the assembly area. The problem was that customer service was also extremely important. With the problems Justin was having with the master schedule, it was difficult to promise order delivery accurately, and equally difficult to deliver the product on time once the order promise was made.
3. The workers-In an effort to control costs, the hourly wage for the workers was not very high. This caused a turnover in the workforce of almost 70% per year. In spite of this, the facility was located in an area where replacement workers were fairly easy to hire. They were assigned to the production area after they had a minimum of one week's worth of training on the equipment. In the meantime, the company filled vacant positions with temporary workers brought in by a local temporary employment service.
4. Engineering changes-The design of virtually all the products was changing, with the average product changing some aspect of the design about every two months. Usually this resulted in an improvement to the products, however, so Justin quickly dismissed the changes as a problem. There were also some engineering changes on the equipment, but in general little in the way of process change had been made. The setup time for a batch of a specific design had remained at about 15 minutes. That forced a batch size of about from 50 to 300 units, depending on the design. The equipment was getting rather old, however, forcing regular maintenance as well as causing an occasional breakdown. Each piece of equipment generally required about three hours of maintenance per week.
Since the computer had done most of his calculations in the past, Justin decided to check to see if the computer was the source of the problem. He gathered information to conduct a manual calculation on a week when there were eight people assigned to the assembly area (one person for each of eight machines) for one shift per day. With no overtime, that would allow 320 hours of production.
Case Analysis
1. With this information, Justin calculated the total standard time required to be within the 320 hours available. Is he correct?
Calculate the time required and check the accuracy of his calculation.
2. List the areas you think are causing trouble in this facility.
3. Develop a plan to deal with the situation and try to get the production schedule back under control under the constraints listed.
How much money can bank a create by making loans
: How much money can Bank A create by making loans? How much money can the banking system as a whole create? (Show calculation).
|
Agricultural sectors and growing unemployment
: The Great Depression (1929)- The stock market crashed and "among the factors contributing to the crash were a trade imbalance following World War I, where the United States was exporting more than it was importing to nations that could not pay;
|
Perform the present worth analysis
: If the five projects above are mutually exclusive alternatives, perform the present worth analysis and select the best alternative
|
Which division provides the highest operating margin
: Which division provides the highest operating margin? Which division provides the lowest after-tax profit margin? Which division has the lowest after-tax return on assets? Compute net income (after-tax) to sales for the entire corporatio..
|
Check the accuracy of his calculation
: With this information, Justin calculated the total standard time required to be within the 320 hours available. Is he correct? Calculate the time required and check the accuracy of his calculation.
|
Tasked with creating an informative essay
: This week, you were tasked with creating an Informative Essay. This essay was a bit different than our last essay because it took a third person point of view and some research to complete!
|
What is the company unlevered cost of equity capital
: Weston Industries has a debt-equity ratio of 1.5. Its WACC is 10.5 percent, and its cost of debt is 6 percent. The corporate tax rate is 35 percent. What is the company's cost of equity capital What is the company's unlevered cost of equity capital W..
|
Write two-pass assembler for subset of mips instruction set
: Write a two-pass assembler for a subset of the MIPS instruction set. It should be able to read an assembly file from the command line and write the object code to standard output.
|
What is the most he should have paid for the annuity
: Mark Ventura has just purchased an annuity to begin payment at the end of 2016 (that is the date of the first payment). Assume it is now the beginning of the year 2014. The annuity is for $20,000 per year and is designed to last 8 years. If the inter..
|