1. Which best describes the NPV of a project?
A. The future monetary value of a project
B. The order in which projects should be undertaken
C. The present value of a projects future cashflows
D. The present value of a project's future cashflows, less the initial cost of the project
E. The value of a project, minus the value of other alternative projects.
2. Which of the following does NOT characterize a functional project structure?
A. projects are embedded within the functional group where the project will be used
B. projects are frequently high-priority in the life of the business unit or division
C. lower project cost than a pure project structure
D. technical knowledge depth
E. the problem of fractional resources is minimized