Q1. Top-down estimates (also called parametric estimates):

a. Are based on historical trends
b. Can be derived from the WBS
c. Can be determined by analyzing work packages
d. Provide accurate assessments of project costs

Q2. The type of management whose focus is on activities whose variances lie outside the acceptable range is:

a. Management by Objectives
b. Management by Exception
c. Management by Walking Around
d. Management by Control Limits

Q3. A key characteristic of an effective project team is that:

a. Members have graduate degrees in project management
b. Members come from the same professional background
c. Members see themselves as stakeholders in the project
d. Members adhere to a prescribed pecking order

Q4. An autocratic management style:

a. Is effective in most project management situations
b. Is effective in highly routine efforts
c. Is effective in high flux, state-of-the-art projects
d. Will lead to the tyranny of the majority

Q5. An effective project manager must:

a. Tell his team members what to do
b. Be the most capable person on the team technically
c. Be focused on achieving results
d. Not trust his team members to achieve results without his personal attention to detail

Q6. An objective of prototyping is to minimize life-cycle cost.

a. true
b. false

Q7. Rapid prototyping is a methodology for:

a. Specifying requirements at the outset and for controlling very tightly any changes to them
b. Specifying requirements at the outset and for facilitating later changes to them with minimum customer in put
c. Triggering early warning of unauthorized changes to the original prototype to enable project management to take remedial actions
d. Working closely with customers by creating and updating prototypes that respond to customer input

Q8. Which of the following is an example of a project?

a. Maintaining e-mail addresses
b. Capacity planning
c. Submitting travel and expense reports
d. Sending monthly reports to top management

Q9. Which of the following is a scope planning tool?

a. Benefit/cost analysis
b. WBS
c. Earned Value analysis
d. Fast tracking

Q10. When crashing a project, we typically choose critical path tasks whose costs of crashing are highest.

a. true
b. false

Q11. A major strength of task Gantt charts is that they can:

a. Offer a sophisticated model of a project
b. Show how many resources will be used on the project
c. Show the interdependencies of tasks
d. Show actual versus planned schedule status

Q12. Good functional requirements

a. Describe how the deliverable should be developed
b. Provide detailed technical insights into what the deliverable will do
c. Describe what the deliverable looks like and what it should do
d. Are created after development of the technical specifications

Q13. If EV = $300, AC = $400, and the project budget is $1,000, what is the estimated final cost of the project (this is known as EAC, estimate at complete)?

a. $750
b. $1,000
c. $1,250
d. $1,333

Q14. The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed.

a. true
b. false

Q15. Scope creep means:

a. Needs emergence and identification
b. Uncontrolled changes to a project's requirements during project execution
c. Migration of project needs to requirements
d. Imprecise scope statement

Q16. When we have objective data on the probability of an event, we are involved with decision making under certainty.

a. true
b. false

Q17. According to PMI, a WBS should focus on

a. Tasks
b. Deliverables
c. Interrelationships among activities
d. Cost of the project

Q18. Bottom-up estimates:

a. Are based on historical trends
b. Can be derived from the WBS
c. Must employ Monte Carlo simulation
d. a and c

Q19. Which of the following is a characteristic of an effective reporting system?

a. SMART
b. KISS
c. MBO
d. LOWBALLING

Q20. Configuration management is a:

a. Methodology for working closely with customers by developing and updating requirements for faster response to changing customer needs
b. Methodology for ensuring that requirements evolve with evolving customer requirements
c. Methodology for specifying requirements at the outset and for controlling very tightly any changes to them
d. Methodology for specifying requirements at the outset and for facilitating any changes to them with minimum customer input

Q21. Ensuring a one-to-one correspondence between specification items and general design items is a feature of:

a. Scope statement definition
b. WBS construction
c. Rapid prototyping
d. Configuration management

Q22. Definitive estimates are generally derived from:

a. Bottom-up estimates
b. Top-down estimates
c. Expert judgment cost estimates
d. Order of magnitude estimates

Q23. A project can be terminated prematurely because the original objectives may no longer be valid.

a. true
b. false

Q24. Confidence in the accuracy of a cost estimate increases when top-down and bottom-up estimates converge.

a. true
b. false

Q25. The resource planning tool that enables us to identify who we need to carry out what tasks is called:

a. A resource Gantt chart
b. A resource matrix (also called the responsibility chart)
c. A resource ogive
d. A resource loading chart (also called a resource histogram)

Q26. If you want to shorten the length of a project, you must:

a. Shorten the critical path
b. Shorten the free float
c. Spend more money
d. Cut back on the features you plan to deliver

Q27. A challenge of the matrix project organization is that:

a. Team members are full of ego
b. Team members are selected from the same functional area
c. Team members have divided loyalties
d. It enables functional managers to provide career guidance to their workers

Q28. The poor man's hierarchy is a method for:

a. Project estimation
b. Project scheduling
c. WBS construction
d. Project selection

Q29. Using working time or elapsed time to calculate the time it will take to complete a task produces the same results.

a. true
b. false

Q30. In resource planning, one of the issues that needs to be considered is:

a. Staff empowerment
b. Technical requirements of the project
c. Theory X management principles
d. Theory Y management principles

Q31. Needs recognition is the first stage of the needs-requirement life cycle.

a. true
b. false

Q32. The bottom-most level of the WBS -- the level at which project budget and schedule data are captured -- is called:

a. Work package
b. Code of accounts
c. Budget baseline
d. Change control level

Q33. The purpose of mid-project evaluation is:

a. Continual monitoring of budget and estimates
b. To focus on achievement of individual element of the project plan
c. To determine whether the original objectives are still relevant
d. To re-baseline the project budget

Q34. Under rapid prototyping (also called application prototyping), the customer actually sees and works with the deliverable as it evolves.

a. true
b. false

Q35. A four step risk assessment process reflecting standard risk management good practice consists of:

a. Risk identification, Risk deflection, Risk impact analysis, Risk monitoring and control
b. b. Risk acceptance, Risk impact analysis, Risk response planning, Risk monitoring and control
c. Risk deflection, Contingency planning, Risk impact analysis, Risk monitoring and control
d. Risk identification, Risk impact analysis, Risk response planning, Risk monitoring and control

Q36. In risk management, insurance is an example of:

a. Risk avoidance
b. Risk deflection
c. Risk acceptance
d. Contingency planning

Q37. A key objective of change control in configuration management is to keep track of actions taken in response to change requests.

a. true
b. false

Q38. If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have?

a. 0.5 hours
b. 1.5 hours
c. 2.5 hours
d. 8.5 hours

Q39. There is a definite link between the level of risk an enterprise encounters and project time frame.

a. true
b. false

Q40. A laissez-faire management style may lead to a ship without rudder syndrome.

a. true
b. false

Reference no: EM13973324

Questions Cloud

Determine the amount of net income savannah will report in : Determine the amount of net income Savannah will report in each of the four quarters of 2012, assuming actual sales are as projected and employing the integral approach to interim financial reporting. Compute Savannah's profit margin on sales for eac..
Describe the concept of strategic groups mapping : Explain the uses and limitations of portfolio management matrices such as the growth-share matrix developed by the Boston Consulting Group (BCG).
What force must be exerted on the smaller piston : If the atmospheric pressure is 1.1Af-10 raise to the power 5 Pa, the corresponding downward force on the top of a horizontal square areas 6cm on each side is approximately. show calculation.
How apply its principles when working with particular client : Create a scenario and explain how you would apply its principles when working with a particular client. Why did you choose this theory
Characteristic of an effective project team : The type of management whose focus is on activities whose variances lie outside the acceptable range is: A key characteristic of an effective project team is that:
Importance of the employee retirement income security act : Classify two (2) pros of an employee using the benefits that the employer provides and at least one (1) con that may be a conflict for an employee using such benefits.Note: Refer to cases in your textbook as you formulate your response
Reflect on personal experiences working for an organization : Reflect on your personal experiences working for an organization, and on how those experiences are, or have been, shaped by logistics. From what you've seen, what is logistics? What do logisticians do?
Decision-making theories - prescriptive and descriptive : There are two types of decision-making theories: prescriptive (those that should be made) and descriptive (and those that are made)
What are the degrees of freedom for this f-statistic : What are the degrees of freedom for this F-statistic and what is the predicted house size (in hundreds of square feet) for an individual earning an annual income of $40,000, having a family size of four, and going to school a total of 13 years?

Reviews

Write a Review

Accounting Basics Questions & Answers

  The company declared and paid cash dividends of 132000 last

megenity companys net income last year was 194000. changes in the companys balance sheet accounts for the year appear

  How much was saturn over or underapplied overhead

Saturn, Inc., which uses a predetermined overhead rate based on direct labor hours, estimated total overhead for the year to be $7,500,000 and total direct labor hours to be 125,000 hours.

  Create the trial balance in the normal structure

Using EXCEL, create the trial balance in the normal structure (current assets, long term assets, current liabilities, etc.). Also, include in the workbook a Cost of Goods Manufactured Statement, an Income Statement, a Retained Earnings Statement, and..

  Accordance with professional pronouncements

For which of the segments would information have to be disclosed in accordance with professional pronouncements? A. Segments A, B, C, and D b. Segments A, B, and C c. Segments A and B d. Segments A and D 57. In January 2011, Post, Inc.

  Determine the predetermined overhead rate

Determine the predetermined overhead rate for the year 2011. Set up a T-account for Factory Overhead and enter the overhead costs incurred and the amounts applied to jobs during the year using the predetermined overhead rate.

  Land to the corporation in exchange

Karen, in forming a new corporation, transfers land to the corporation in exchange for the 100 percent of the stock of the corporation. Karen's basis in the land is $275,000, and the corporation assumes a liability on the property in the amount of..

  Operating leverage and forecasting problems

Please complete the following problems and place them in your assignments section by midnight of the last day of the week assigned.  When calculating earnings per share and PE ratios, please show your work.  This problem is similar to the examples..

  Recognize and define the accounting equation

Recognize and define the accounting equation, classify accounts as Assets, Liability, or Equity, and evaluate, record and post common business transactions.

  Tranter inc is considering a project that would have a

tranter inc. is considering a project that would have a ten-year life and would require a 1200000 investment in

  You are the senior accountant responsible for recording

you are the senior accountant responsible for recording accrued liabilities at the end of the companys fiscal year.

  A partnership of attorneys in the st louis missouri area

a partnership of attorneys in the st. louis missouri area has the following balance sheet accountsas of january 1

  Lenat company produced 50000 units during the year variable

lenats contribution income statement utilizing variable costing appears below lenat company income statement for the

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd