Characteristic of a project

Assignment Help Physics
Reference no: EM133263120

Exercise Quiz for practice, any expert tutor can help to review and answer for below quiz? If have some explanation one each question, will be appreciated.

1. Which of the following is NOT considered to be a characteristic of a project?

A. An established objective

B. A clear beginning and end

C. Specific time, cost and performance requirements

D. For internal use only

E. Something never been done by a particular company before

2. Which of the following activities is NOT considered a project?

A. Developing a new software program

B. Designing a space station

C. Preparing the site for the Olympic Games

D. Production of automobile tires

E. Developing a new advertising program

3. In the________ stage of What is a Project?, a major portion of the actual project work performed.

A. Identifying

B. Defining

C. Planning

D. Executing

4. Which of the following is NOT typical of a project manager?

A. Managing a temporary activity

B. Overseeing existing operations

C. Managing a nonrepetitive activity

D. Responsible for time, cost and performance trade-offs

E. Work with a group of outsiders, including vendors and suppliers

5. Which of the following statements is true?

A. Project management is far from a standard way of doing business.

B. Project management is increasingly contributing to achieving organizational strategies.

C. Project management is being used at a consistent percentage of a firm's efforts.

D. Project management is a specialty that few organizations have access to.

E. All of these statements are false.

6. Project governance does NOT include

A. Setting standards for project selection.

B. Overseeing project management activities.

C. Centralization of project processes and practices.

D. Options for continuous improvement.

E. Allowing project managers to plan the project the way they see fit.

7. Project should align with the organization's overall strategy in order to

A. Complete the project safely.

B. Reduce waste of scarce resources.

C. Ensure customer satisfaction.

D. Secure funding.

E. None of these are reasons why projects should align with the organization's overall strategy.

8. Which of these is NOT part of the "sociocultural dimension" of project management?

A. Negotiation

B. Resource allocation

C. Managing customer expectations

D. Leadership

E. Dealing with politics

9. Governance of all project management processes and procedures helps provide senior management with all of the following EXCEPT

A. A method to ensure projects that are important to senior management are being implemented.

B. An assessment of the risk their portfolio of projects represents.

C. An overview of all project management activities.

D. A metric to measure the improvement of managing projects relative to others in the industry.

E. A big picture of how organizational resources are being used.

10. Which of the following is NOT true about an organization's strategy?

A. Strategy determines how an organization will compete.

B. Strategy is implemented through projects.

C. Only top management must understand strategy.

D. Project selection should be clearly aligned with strategy.

E. Project management plays a key role in supporting strategy.

11. Which of the following is NOT true about organizational politics?

A. Project managers should not engage in organizational politics.

B. Politics can have a significant influence on which projects receive funding.

C. Politics exist in every organization.

D. Politics can influence project selection.

E. Politics can play a role in the aspirations behind projects.

12. Which of the following is NOT one of the requirements for successful implementation of strategies through projects?

A. Allocation of resources

B. Prioritizing of projects

C. Motivation of project contributors

D. Adequate planning and control systems

E. Quality management

13. Project are usually classified into all but one of the following categories. Which one is NOT one of the typical classifications?

A. Compliance and emergency

B. Operational

C. Strategic

D. Political necessity

E. All of these are typical classifications.

14. A project screening matrix typically contains all of the following EXCEPT

A. The list of available projects.

B. Specific criteria.

C. Weights assigned to specific criteria.

D. Costs to complete each project.

E. All of these are typically contained.

15. Which of the following is true of multi weighted scoring models?

A. Will include quantitative criteria

B. Will include qualitative criteria

C. Each criterion is assigned a weight.

D. Projects with higher scores are considered more desirable.

E. All of these are true.

16. When a prioritization team is balancing projects, they consider all factors expect for

A. risk.

B. resource demand.

C. leadership style.

D. type of project.

17. Project managers should not engage in organizational politics.

A. True

B. False

18. Which of the following is NOT true of project management structures?

A. They provide a framework for launching and implementing projects.

B. They appropriately balance the needs of both the parent organization and the project.

C. In selecting a management structure, the culture of the organization is not a huge consideration.

D. The project itself should be considered when determining which structure is best.

E. They help determine who has most authority in regard to managing the project.

19. At the project level, which of the following is a factor that should influence the choice of project management structure?

A. The size of the project

B. The novelty of the project

C. Budget and time constraints

D. The strategic importance of the project

E. All of these are factors that should influence the choice of project management structure.

20. Which are the three different matrix systems discussed in the text?

A. Functional, Weak, Strong

B. Balanced, Functional, Projectized

C. Weak, Strong, Balanced

D. Neutral, Weak, Strong

E. Functional, Neutral, Projectized

Reference no: EM133263120

Questions Cloud

Adopting the vertical integration strategy : A car manufacturer in Asia is interested in adopting the vertical integration' strategy. What specific options would you suggest to the manufacturer and why?
Adopting new technologies based on your experience : Describe your biggest challenge in adopting new technologies based on your experience?
What proportion of accidents involved more than one vehicle : Texting while driving is a problem. Maryland Department of Motor Vehicles commissioned a study and found on average 400 accidents occur on the DC beltway every
How can she protect herself against lawsuits : What kind of legal exposure does Wanda have, and how can she protect herself against lawsuits?
Characteristic of a project : 1. Which of the following is NOT considered to be a characteristic of a project?
Convicts on multiple charges of fraud : The magistrate, M, convicts A on multiple charges of fraud, and proceeds to the sentencing phase without giving the reasons for arriving at the verdicts
What is the project completion date : Bolling Electronics manufactures DVD players for commercial use. W. Blaker Bolling, president of Bolling Electronics, is contemplating producing DVD players for
Food insecurity project plan : As part of the Ottawa, Canada, food insecurity project plan, what role does Smart farming play, along with the federal and provincial governments, non-profit or
Value-added flow charting : Please provide detailed process map with all tasks, decision points and loopbacks for a function that you are responsible for or familiar with.

Reviews

Write a Review

Physics Questions & Answers

  Find the magnitude of the resulting magnetic field

A sphere of radius R is uniformly charged to a total charge of Q. It is made to spin about an axis that passes through its center with an angular speed ω. Find the magnitude of the resulting magnetic field at the center of the sphere.

  Find the equivalent resistance

A resistor is in the shape of a cube, with each side of resistance  R . Find the equivalent resistance between any two of its adjacent corners.

  What is the electric field at the location

Question: Field and force with three charges? What is the electric field at the location of Q1, due to  Q 2 ?

  What is the maximum displacement of the bridge deck

What is the maximum displacement of the bridge deck?

  What is the magnitude of the current in the wire

What is the magnitude of the current in the wire as a function of time?

  Blackbody

Questions on blackbody, Infra-Red Detectors & Optic Lens and Digital Image.

  Gravity conveyor

Illustrate the cause of the components accelerating from rest down the conveyor.

  Calculate the dc voltage

Calculate the dc voltage applied to the circuit.

  Quadrupole moments in the shell model

Quadrupole moments in the shell model

  Determine the tension in each string

Determine the tension in each string

  Introductory mechanics: dynamics

Calculate the smallest coefficient of static friction necessary for mass A to remain stationary.

  Evaluate maximum altitude

Evaluate maximum altitude?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd