Challenges addressed by lean

Assignment Help Project Management
Reference no: EM132485387

1. Methodology of six sigma moves through 5 steps, which of following is not one of them.

A. analyze

B. measure

C. control

D. install

2. Minimizing waste is not one of the objective of Six sigma.

A. True

B. False

3. Which of the following is one of the challenges addressed by lean?

A. Eliminating the process variability

B. Establishing standards for quality control.

C. Minimizing process delays.

D. Maximizing return on invested capitol.

4. Establishing ----- is necessary when creating process control chart.

A. Lower control Limit

B. Upper Control Limit

C. Target or Centerline

D. All of the above

5. Which of the following is used to identify and display inputs, suppliers, outputs, process and customers

A. Y = f(x)

B. Value stream map

C. SIPOC

D. Fisher bone Diagram

6. A process output target or centerline is positioned below the ---- on the control chart.

A. Lower control limit

B. Upper control limit

C. Lower specification Level

D. Not enough information given

7. Which of the following defines the relationship between process inputs and outputs.

A. X= Y

B. Y = F( X)

C. X = Y(F)

D. Y= X

8. The term value added in lean refers to ----

A. The section of those suppliers and vendors who deliver at lowest cost.

B. The improvement in process efficiency by adding new features to a product.

C. Delivering value for a product or service from the customer perspective

D. Delivering value for a product or service from the project teams perspective.

9. A value stream map is also called a process flow chart is used in six sigma to analyze the variability of a process.

A. True

B. False

10. One of the object in lean is to minimize or eliminate --

A. Value added activities

B. Activity variance

C. Non value- added activities

D. Product Failures

Reference no: EM132485387

Questions Cloud

Project close-lessons learned sessions : In the project schedule, you have scheduled project close-lessons learned sessions to occur throughout the project. What are three benefits for doing this?
Kinds of operating expenses : They also have to consider the expenses they will face to operate the car after they buy it. What kinds of operating expenses should they include?
What is the? price by book ratio : There are 54,000 shares of common stock outstanding. What is the? price/book ratio? What does this indicate about how shareholders view? Chang, Inc.?
Please identify the attributes and primary keys : 1. Please identify the attributes and primary keys needed for each of the entities.
Challenges addressed by lean : Which of the following is one of the challenges addressed by lean?
Write out which accounts increased for each transaction : For each situation, write out which accounts increased or decreased for each transaction and the amount of the increase or decrease.
What percent of annual life-cycle cost is related to fuel : If the MARR is 15% per year, what is the annual equivalent life-cycle cost of the gas turbine? What percent of annual life-cycle cost is related to fuel?
What will the earnings per share be after the merger : What will the earnings per share be after the merger? Firm XY is planning on merging with Firm YZ. Firm XY will pay Firm YZ's shareholders the current value
What is the value of cpi after the acquisition : What is the value of CPI after the acquisition? CPI Inc is acquiring JW for R470 000 in cash. CPI has 27000 shares outstanding at market value

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd