MUST SHOW ALL EQUATIONS USING EXCELL FORMATTING

Scenario Data: The mean time required to complete a certain type of construction project is 61 weeks with a standard deviation of 4.15 weeks.

Answer questions 1 - 4 using the preceding information and modeling this situation as a normal distribution.

Question 1. What is the probability of the completing the project in no more than 58 weeks?

Question 2. What is the probability of the completing the project in more than 62 weeks?

Question 3. What is the probability of completing the project between 58 weeks and 65 weeks?

Question 4. What is the probability of completing the project within plus or minus one standard deviation of the mean?

Reference no: EM131305681

Questions Cloud

The performance management system : NewLearning Pty Ltd develops online learning courses for clients in the Asia-Pacific region and specialises in the development of courses for supervisor development. The courses are tailor-made to meet client’s needs and specifications. What form of ..
Strategically significant differences between NFPs and FPs : Long-term planning for government and other public type agencies is difficult because. When timing their corporation’s entry into the capital market, managers must carefully consider the current state of the capital markets, the current capital struc..
Understand by the concept of the learning organisation : WBD Enterprises is a web design company that is competing on a global basis. The company has 40 employees, including two who specialize in marketing the company’s web design services. This niche is highly competitive with many global operators. What ..
Certain type of construction project : The mean time required to complete a certain type of construction project is 61 weeks with a standard deviation of 4.15 weeks. What is the probability of the completing the project in no more than 58 weeks? What is the probability of the completing t..
Certain type of construction project : The mean time required to complete a certain type of construction project is 61 weeks with a standard deviation of 4.15 weeks. What is the probability of the completing the project in no more than 58 weeks? What is the probability of the completing t..
Many applications of law primarily affect individuals : Many applications of law primarily affect individuals, such as buying or selling personal property. Critique the amount and kinds of protection provided to individuals and whether you think that the law provides too much protection, limiting individu..
Consider the numerous laws that affect businesses : Consider the numerous laws that affect businesses and evaluate the regulatory climate in which they operate. Does it seem that there are too many regulations or too few?
Normal time to perform a repetitive manual assembly task : The normal time to perform a repetitive manual assembly task is 4.25 min. In addition, an irregular work element whose normal time is 1.75 min must be performed every 8 cycles. Determine the standard time per piece and how many work units are produce..
Provide marketing communication plan to students : Assume you are a textbook publisher. You have been selling books to students through bookstores. Now with the advent of iPads and e-readers, you have decided to bypass bookstores completely. Provide a marketing communication plan to students. Provide..

Reviews

Write a Review

Operation Management Questions & Answers

  Major hardships facing expatriates on their return home

Based on Chapters 3 and 4, analyze two (2) of the major hardships facing expatriates on their return home after a lengthy assignment. What would your biggest challenge be if you were an expatriate?

  A position analysis questionnaire analyzes

A position analysis questionnaire analyzes all of the following job aspects except:

  How come you choose to do this for product b

How come you choose to do this for product B and not product A? My other question is product A does not meet customer demand as it drops down to 49000.

  What factors may dictate the need for multiple models

Multiple models are often used in supporting business decision making. Why might this be the case and what factors may dictate the need for multiple models?

  Describe the differences between productivity

Describe the differences between productivity and its subcomponents (total measure productivity, partial measure productivity

  Total permanent disability or to benefits described

Laura was a painter until a malicious coworker splashed solvent in her eyes, seriously reducing the quality of her eyesight. According to the workers' compensation law in Laura's state, she might be entitled either to damages based on the percentage ..

  Using simple random sampling procedure

A consultant had administered a questionnaire to some 285 employees using a simple random sampling procedure. As she looked at the responses, she suspected that two questions might not have been clear to the respondents. She would like to know if her..

  What is the nature of the conflict

Discuss how to find a value (cost) for the time customers spend in line. The text uses numbers like $8.00 per hour or $25.00 per hour. Would your assessment of this value (as a customer) be different from your assessment (as a business manager)? How?..

  Draw a supply-demand diagram of the market

Draw a supply/demand diagram of the market for "loanable funds" in the U.S. Use the "interest rate" as the "price" of loanable funds on your diagram. Show the effects of a rise in the expected inflation rate on your diagram.

  About family owned business-through a rough patch

First off, I'd like to say this book was an easier read for me than the previous three. I liked how personable it was and I felt like I could relate to the "story" better than the other books. With that being said, the story is about a family owned b..

  Discuss the types of issues this agency addresses

Describe the function, mission and scope (work) of the federal agency you have selected - Discuss the types of issues this agency addresses.

  What is the amount of his new annual payment

Robert is repaying a debt with 21 annual end-of-the-year payments of $1300 each. At the end of the 4th year, he makes an extra payment of $2600. He then refinances his loan by reducing his remaining payment period by 2 years and making level payments..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd