Case Study: The Automated Evaluation Project 

"No deal!" said the union. "The current method of evaluating government employees at this agency is terrible, and if a change doesn't occur, we'll be in court seeking damages." 

In 1984, a government agency approved and initiated an ambitious project, part of which was to develop an updated, automated evaluation system for the 50,000 employees located throughout the United States. The existing evaluation system was antiquated. Although forms were used for employee evaluation, standardization was still lacking. Not all promotions were based on performance. Often they were based on time in grade, the personal whims of management, or friendships. Some divisions seemed to promote employees faster than others. The success or failure of a project could also seriously impact performance opportunities. Some type of standardization was essential. 

In June 1985, a project manager was finally assigned and brought on board. The assignment of the project manager was based on rank and availability at that time rather than the requirements of the project. Team members often possessed a much better understanding of the project than did the project manager. 

The project manager, together with his team, quickly developed an action plan. The action plan did not contain a work breakdown structure but did contain a statement of work which called out high-level deliverables that would be essential for structure analyses, design and programming. The statement of work and deliverables were more in compliance with agency requirements for structured analyses, design, and programming than with the project's requirements. The entire action plan was prepared by the project office, which was composed of eight employees. 

Bids from outside vendors were solicited for the software packages, with the constraint that all deliverables must be operational on existing agency hardware. In October 1985, the award was made by the project office to Primco Corporation with work scheduled to begin in December 1985. 

In the spring of 1986, it became apparent that the project was running into trouble and disaster was imminent. Three major problems faced the project manager. As stated by the project manager: 

  1. The requirements for the project had to be changed because of new regulations for government worker employee evaluation. 
  2. Primco did not have highly skilled personnel assigned to the project. 
  3. The agency did not have highly skilled personnel from the functional areas assigned to the project. 

The last item was controversial. The line managers at the agency contended that they had assigned some of their best people and that the real problem was that the project manager was trying to make all of the decisions himself without any input from the assigned personnel. The employees contended that proper project management practices were not being used. The project was being run like a dictatorship rather than a democracy. Several employees felt that they were not treated as part of the project team.  

According to one team member:  

"The project manager keeps making technical decisions without any solid foundation to support his views. Several of us in the line organization have significantly more knowledge than does the project manager, yet he keeps overriding our recommendations and decisions. Perhaps he has the right, but I dislike being treated as a second-class citizen. If the project manager has all of his technical knowledge, then why does he need us?" 

In June 1986, the decision was made by the project manager to ask one of the assistant agency directors to tell the union that the original commitment date of January 1987 would not be met. A stop-work order was issued to Primco, thus canceling the contract. 

The original action plan called for the use of existing agency hardware. However, because of unfavorable publicity about hardware and software problems at the agency during the spring of 1986, the agency felt that the UNIVAC System would not support the additional requirements, and system overload might occur. Now hardware, as well as software, would be needed. 

To help maintain morale, the project manager decided to perform as much of the work as possible in-house, even though the project lacked critical resources and was already more than one year late. The project office took what was developed thus far and tried to redefine the requirements. 

With the support of senior management at the agency, the original statement of work was thrown away and a new statement of work was prepared. "It was like starting over right from the beginning," remarked one of the employees. "We never looked back at what was accomplished thus far. It was a whole new project!" With the support of the agency's personnel office, the new requirements were finally completed in February of 1987. 

The union, furious over the schedule slippage, refused to communicate with the project office and senior management. The union's contention was that an "illegal" evaluation system was in place, and the current system could not properly validate performance review requirements. The union initiated a lawsuit against the agency seeking damages in excess of $21 million. 

In November 1986, the procurement went out for bids for both hardware and a database management system. The procurement process continued until June 1987, when it was canceled by another government agency responsible for procurement. No reason was ever provided for the cancellation. 

Seeking alternatives, the following decisions were made: 

  1. Use rented equipment to perform the programming. 
  2. Purchase a database management system from ITEKO Corporation, provided that some customization could be accomplished. The new database management system was scheduled to be released to the general public in about two months. 

The database management system was actually in the final stages of development. ITEKO Corporation promised the agency that a fully operational version, with the necessary customization, could be provided quickly. Difficulties arose with the use of the ITEKO package. After hiring a consultant from ITEKO, it was found that the ITEKO package was a beta rather than a production version. Despite these setbacks, personnel kept programming on the leased equipment with the hope of eventually purchasing a Micronet Hardware System. ITEKO convinced the agency that the Micronet hardware system was the best system available to support the database management system. The Micronet hardware was then added to the agency's equipment contract but later disallowed on September 1987, because It was not standard agency equipment. 

On October 1987, the project office decided to outsource some of the work using a small/minority business procurement strategy for hardware to support the ITEKO package. The final award was made in November 1987, subject to software certification by one of the agency's logistics centers. Installation in all of the centers was completed between November and December 1987. 

QUESTIONS 

  1. Is there anything in the case that indicates the maturity level of project management at the agency around 1985-1986? 
  2. What are the major problems in the case? 
  3. Who was at fault? 
  4. How do you prevent this from occurring on other projects? 
  5. Based on the topics covered in class thus far, which communication tool would help in this dilemma? Name one communication tool and state the reason why it would be helpful in this situation (Your answer here should be different from the answers you provided on previous case studies).  
  6. Draft a sample of this tool (don't just provide a blank template; make sure it is completely filled out). 

Reference no: EM133223624

Questions Cloud

What are some other things your team will need : Be sure to include new start-up and e-commerce risks. What are some other things your team will need to consider during the planning phase for this audit
Information-systems component needed for the project : Wilmont's is three months into a major project, and the individual who had been in the role of project manager information systems left suddenly, leaving the pr
Influence of these policies and events : Influence of these policies and events on your own cultural competence and the social and cultural influences on your understandings.
Discuss long-run economic growth : Discuss Long-Run Economic Growth? Will the poor countries catch up to rich countries by growing faster?
Case study-the automated evaluation project : "No deal!" said the union. "The current method of evaluating government employees at this agency is terrible, and if a change doesn't occur, we'll be in court s
Importance of european worldview and african displacement : Discuss both the importance of the European Worldview and African Displacement and how it is shifting. Bold the titles of any texts as you discuss them
Developing a recruiting message for a survey : When developing a recruiting message for a survey, you should include the following: I. Who you are II. How long it will take III.
Write a discussion about international marketing : Write a discussion about International Marketing. Something I found interesting and would like to explore further is the marketing strategies
Monopolist encounters linear demand curve : A monopolist encounters a linear demand curve should always produce at the point where the demand is unit elastic in order to maximise profit.

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd