Capability index (cpk) formulas to compute the two values

Assignment Help Project Management
Reference no: EM1392138

You have just used the capability index (Cpk) formulas to compute the two values "min [2, 2.5]." Which of the following is the proper interpretation of these numbers?

A) The true capability index value is 2.5
B) The mean of the production process has shifted to the left of the design limits
C) The mean of the production process has shifted to the right of the design limits
D) The mean has not shifted at all
E) The true capability index value is between 2 and 2.5

Reference no: EM1392138

Questions Cloud

Process helps improve quality and productivity : The Malcolm Baldrige award selection process helps improve quality and productivity by which of the following means?
Explain different culture of different society : Culture can be seen in every society if you know building blocks of it. Write down 1000 word essay about the culture which you encountered that is different from your daily culture.
Conditional values and probabilities : Construct a decision table for this problem. Include all conditional values and probabilities in the table.
Description of probability calculations-normal distribution : A soft drink company has recently received customer complaints about its one-liter-sized soft drink products. Customers have been claiming that the one-liter-sized products contain less than one liter of soft drink.
Capability index (cpk) formulas to compute the two values : You have just used the capability index (Cpk) formulas to compute the two values "min [2, 2.5]." Which of the following is the proper interpretation of these numbers?
Information about normal probability distribution : The monthly income of residents of Dayton is normally distributed with a mean of $3000 and a standard deviation of $500.
Why is a normal distribution called normal : Why is a normal distribution called "normal"? Investigate the answer to this question on the internet and share the answer in your own words. Be sure to cite your sources.
Testing an esp clalim : A coin is tossed 20 times. A person, who claims to have ESP is asked to predict the outcome of each flip in advance. She predicts correctly on 14 tosses.
Stimulating foreign based suppliers of american companies : The Malcolm Baldrige award selection process helps improve quality and productivity by which of the following means? Stimulating foreign based suppliers of American companies to improve quality

Reviews

Write a Review

Project Management Questions & Answers

  Developer''s desire to use new languages

developer who is requesting to complete his current project using the newly-released Belchfire 500. What will your answer be, and why?

  Prepare a comprehensive project scope analysis

The conceptual development process, scope statement and statement of work that will clearly detail the projects expectation , problems , goals, objective, and aids in the projects communications with stake holders

  Show healthcare management quality practices

How would applying the core values and concepts of the Baldridge Health Care Criteria for performance Excellence improve health care quality

  What are the criteria for selecting items for analysis

How do you determine if the project is sensitive to the specific items and what are the criteria for selecting items for analysis?

  Explaining member of a manager-managed llc

Eric is a member of a manager-managed LLC but is not a manager. This LLC invests in real estate and manages it as rental property in a college town.

  What are the three project team structures

What are the three project team structures and what are some of the elements that differentiate the team structures from one another

  Objective of project meet constraints of quality and cost

The objective is that the project may meet the constraints of quality, cost and schedule in time.

  Project-s net present value if rate of return is given

What is the project's net present value if the required rate of return is 10 percent?

  Optimum cost-time schedule for the project

What is the optimum cost-time schedule for the project and the cost?

  What are possible steps included in project closure

What are possible steps included in project closure and have you been a part of a project that did not end successfully

  Assessment into a security management program

Quality assurance is essential to any security management program and how can we incorporate quality assessment into a security management program?

  Develop a cost estimation for a project

Information Systems Questions - What elements need to be considered in developing a cost estimation for a project?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd