Calculating variance for the project activities

Assignment Help Project Management
Reference no: EM1336942

Q1) Given this information about an activity: ES = 10, EF = 15, LS = 26, and LF = 31. The amount of slack associated with the activity is?

Q2) Using the following project information, calculate the variance for each of the project activities.

Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s)
A 3 6 9 none
B 3 5 7 A
C 4 7 12 A
D 4 8 10 B
E 5 10 16 C
F 3 4 5 D,E
G 3 6 8 D,E
H 5 6 10 F
I 5 8 11 G
J 3 3 3 H,I

Reference no: EM1336942

Questions Cloud

Calculating completion time for the project : Calculate the completion time for the project. (Completion time = weeks)
Computing unlevered beta : Morgan Entertainment has a levered beta of 1.20. The firm's capital structure consists of 40% debt and 60% equity-Find out Morgans's unlevered beta?
What is the best way to write down the value ''7564'' : What is the best process to write the value '7564' and make it clear to the reader that the number should be interpreted as a hexadecimal value?
Discuss what has occurred to change the demand : Assume the basis for the trends in consumption patterns as discussed in the article. Discuss what has occurred to change the demand for, or the supply.
Calculating variance for the project activities : Using the following project information, calculate the variance for each of the project activities.
Explain how do you calculate the expected intrinsic value : Explain How do you calculate the expected intrinsic value of the stock for Xavier Company
Optimal capital structure for time warner : Discuss the optimal capital structure for Time Warner in light of current, business, economic, and industry trends.
What information is define by multiplicity on an association : What information is shown by multiplicity on an association end. I want to provide an example demonstrating my explanation that does not come from the ATM example.
Steve jobs leadership : How has Apple Computers, under Steve Jobs' leadership, managed to become a major world company, since 1997 (10 years)?

Reviews

Write a Review

Project Management Questions & Answers

  Capital revenue in the public sector

Specification Stage, Design Stage, Build Stage, Capital revenue in the Public Sector, recurrent revenue in the Public Sector, Policy Framework (PF),  Vision Statement, Mission Statement

  Different internet access technologies

What are the different Internet access technologies you can use to connect to the Internet?

  Reviewing the balanced scorecard approach

Reviewing the balanced scorecard approach of Youngblood and Collins.

  Explaining planning a scrupulous effort

Taking a cue from the above, planning is a scrupulous effort that needs to be well documented in order for projects to succeed.

  Critical issues faced by managers

Identify the most critical issues faced by managers with regard to the topic.

  Earned value management to manage project costs

What is Earned Value Management (EVM)? How can EVM be used to effectively manage project costs?

  Basic service blueprint for ebags current product line

Develop a basic service blueprint for eBAGS' current product line. After analyzing your blueprint, would you recommend to eBAGS managers that they consider business process reengineering?

  Responsibility of project manager-matrix-type organization

What are the responsibilities of a project manager in a matrix-type organization? What about project-type organizations?

  Describing the purpose of attributes of a project

Using the concepts within the textbook "A Not-for-Profit Organization" , outline some attributes of a project, and describe their overall purpose.

  What do you understand by net present value

You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Percentage of-sales approach to advertising budgeting

American Express marketers say they do not use the percentage-of-sales approach to advertising budgeting because if sales decrease in the segment, so will their budget.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd