Calculating completion time for the project

Assignment Help Project Management
Reference no: EM1336946

Use the following project information.

Activity Activity Time(weeks) Immediate Predecessor(s)
A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F

Calculate the completion time for the project. (Completion time = weeks)

Determine which activities are included on the critical path.

A, B, D, F, G
A, B, C, E, G

Reference no: EM1336946

Questions Cloud

Write down a function that uses a switch statement : An airline vice president in charge of operations needs to find out whether the current estimates of flight times are accurate. because there is a larger possiblity of variations due to wether and air traffic in the longer flights, he allows a larg..
Question on capital structure and leverage : Millman Electronics will produce 60,000 stereos next year. Varibable costs will equal 50% of sales-what price must each widget be sold for the company to achieve an EBIT
Suppose that the accident at chernobyl had no effect : You should suppose that the accident at Chernobyl had no effect on the price of hot dogs or Jane's preference of caviar.
Article of medical negligence online : Find a published case or article of Medical Negligence online. Research and 2 pages double space report. Must include the following guidelines in the research: Was there an apparent failure for the medical care practitioner to provide services rend..
Calculating completion time for the project : Calculate the completion time for the project. (Completion time = weeks)
Computing unlevered beta : Morgan Entertainment has a levered beta of 1.20. The firm's capital structure consists of 40% debt and 60% equity-Find out Morgans's unlevered beta?
What is the best way to write down the value ''7564'' : What is the best process to write the value '7564' and make it clear to the reader that the number should be interpreted as a hexadecimal value?
Discuss what has occurred to change the demand : Assume the basis for the trends in consumption patterns as discussed in the article. Discuss what has occurred to change the demand for, or the supply.
Calculating variance for the project activities : Using the following project information, calculate the variance for each of the project activities.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd