Calculating annual project free cash flowin the spring of

Assignment Help Project Management
Reference no: EM13363063

Calculating Annual Project Free Cash Flow

In the spring of 2010, Jemison Electric was considering an investment in a new distribution center. Jemisons CFO anticipates additional earnings before interest and taxes (EBIT) of $ 100,000 for the first year of operation of the center in 2011, and, over the next five years, the firm estimates that this amount will grow at a rate of 5% per year. The distribution center will require an initial investment of $ 400,000 that will be depreciated over a five- year period toward a zero salvage value using straight-line depreciation of $ 80,000 per year. Furthermore, Jemison expects to invest an amount equal to the firms annual depreciation expense to maintain the physical plant. These additional capital expenditures will also be depreciated over a period of five years toward a zero salvage value. Jemisons CFO estimates that the distribution center will need additional net working capital equal to 20% of new EBIT (i. e., the change in EBIT from year to year). Assuming the firm faces a 30% tax rate, calculate the project's annual project free cash flow (FCF) for each of the next five years.

Reference no: EM13363063

Questions Cloud

Consulting plan and recommendationsthe case recruiting : consulting plan and recommendationsthe case recruiting brigade budget department where failures to obligate yearly
Project management and decision makingrespond to the : project management and decision makingrespond to the following in discussion- who approves and reject changes to the
Tying in resources to projectssome companies choose not to : tying in resources to projectssome companies choose not to tie resources to their projects. in what ways does this
Aligning a project with business goalsyou know you need to : aligning a project with business goalsyou know you need to ensure that this project is aligned with business goals.
Calculating annual project free cash flowin the spring of : calculating annual project free cash flowin the spring of 2010 jemison electric was considering an investment in a new
Extimate project effortcosts such as salaries and equipment : extimate project effortcosts such as salaries and equipment rental are a more cut and dry expenses to estimate than the
The following activities are part of a project to be : the following activities are part of a project to be scheduled using cpmactivity intermediate predecessor time weeksa
Project charter importanceexplain the importance of a : project charter importanceexplain the importance of a project charter to the project manager. how does a strong project
Project management plan and phasesshow three important : project management plan and phasesshow three important items that belong within a project management plan and the

Reviews

Write a Review

Project Management Questions & Answers

  Identify strategies that need to be reviewed

Identify strategies that need to be reviewed before an investor can reach his/her personal goals. Discuss the advantages and disadvantage to each strategy.

  Your company has an average annual inventory

Your company has an average annual inventory of $70 million. Its annual cost of goods sold (COGS) is $560 million. Order costs are $195 per order

  Create a fictional information technology project include

Create a fictional information technology project include: a project charter,requirement documents, WBS, schedules, staffing plans, budgets, risk management plans, communication -plans, change management plans based on text Information Technology pro..

  Organisation is bidding for a construction project

Organisation is bidding for a construction project

  Question related to depreciation tax shield

The company has a marginal tax rate of 34 percent and what is the value of the depreciation tax shield?

  Show the project management and decision making

Who approves and reject changes to the scope of the project and who approves and reject resources

  Risk management in any environment

Are you directed not to take risks, or does your company encourage risk taking if you can justify the results perhaps having a greater reward than the costs

  Speculating the deliverables of the project

Also, speculate the deliverables you would provide if you are working on the project.

  How many kanbans do you need for this connector

After several hours of analysis, you develop the following data for scanner connectors used in one work cell. How many kanbans do you need for this connector?

  Project management theory-constraints and disruptions

Constraints and Disruptions - What are your most important considerations when building a project schedule?

  Project management-manage stakeholder expectations

Explain how would you work with a stakeholder who threatens to go over your head and complain to your supervisor if you cannot guarantee specific results

  Important things management do to create quality culture

Applying your knowledge of TQM, what are the most important things that management can do to create a quality culture?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd