Using High-Low to Calculate Predicted Total Variable Cost and Total Cost for a Time Period that Differs from the Data Period Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected:
Month Labor Cost Employee Hour
January $6,900 340
February 9,799 530
March 8,040 620
April 9,687 590
May 8,390 460
June 7,431 330
July 9,390 550
August 7,350 290
Assume that this information was used to construct the following formula for monthly labor cost.
Total Labor Cost = $6,744 + ($2.09 X Employee Hours)
Required:
Assume that 4,200 employee hours are budgeted for the coming year. Use the total labor cost formula to make the following calculations:
Question 1. Calculate total variable labor cost for the coming year. Round your answer to the nearest dollar.
Question 2. Calculate total fixed labor cost for the coming year. Round your answer to the nearest dollar.
Question 3. Calculate total labor cost for the coming year. Round your answer to the nearest dollar.
Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.
Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.
Prepare a master budget for the three-month period.
Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.
Evaluate the Predetermined Overhead Rate
Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.
Complete the schedule to compute the pool rates for the different activities.
Prepare Company financial statements
This individual assignment is based on the TerraCycle Inc.
Discuss the ethical issues
Calculate the GDP in Income Approach and Expenditure Approach
A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd