Calculate total cost of the Development at July value

Assignment Help Project Management
Reference no: EM132245629

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - City Highrise Complex Development Option

The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises.

Assume that you have been appointed as a financial consultant by an investment company to carry out a financial feasibility study for the proposed Office Development Complex Project.

Prepare a report with your recommendations to the Director of the Investment Company to justify the financial viability of this proposed development.

After the submission you will be called for an interview to discuss your findings. This interview will be held within two weeks of your report submission. It is your responsibility to organise a time for an interview.

CITY HIGHRISE DEVELOPMENT COMPLEX -

You have been appointed as a financial consultant by an Investment Company to carry out financial analysis for the proposed City Highrise Complex (Refer the given data and information). Prepare a report with your recommendations to the Managing Director of the company to justify the financial viability of this proposed development.

Development Proposal: Project Details

Office complex development which will have:

  • 75,000 m2 of lettable area
  • 5,000 m2 of lettable retail area

The site is located in the CBD of Melbourne.

Due to high demand it is believed that 100% of the office and retail areas will be fully let.

The Investment Company will purchase this location at a cost, inclusive of legal fees, commissions, etc., of $70.0 million on 1st July 2018.

The company also has decided to demolish the existing building and the demolition work and the new project is to start on 1st October, 2018.

Total development period is expected to be 36 months.

DEVELOPMENT COST -

Land and acquisition costs are $70 Million based upon purchase 1 July 2018, settlement 30 September 2018. Deposit payable 10%. Balance on settlement.

Demolition estimate $800,000. Planning and Design cost is estimated to be $3.5 million. Landscaping and external work cost $500,000. All costs are based on 1st of July 2018 value.

Project commencement 1/10/2018

Planning and design period 6 months

Demolition 3 months

Construction duration 20 months

Landscaping & External 6 months

Cost of design and construction incl. all margins $350 Million (Split $50m + $300 million)

Rise & Fall only during construction

(a) 40% of money spent in first 12 months, with inflation rate of 3%.

(b) Balance of money spent in second 12 months, with 6% inflation in that year.

Allow costs during the development period at $500,000 per annum.

Assume that gross revenue will attract leasing and sales costs of 10% in the first year of operation.

Assume that all cash expenditure bears interest at the rate of 12% per annum.

Allow for the developers' overhead costs of 3% of all cash expended, and a contingency of 5%.

PROJECT REVENUE -

Total office lettable area amounts to 75,000m2 which will be let at an average of $550/m2. Calculate the 'on completion' rental assuming 4% annual escalation.

Total retail lettable area amounts to 5,000 m2 which will be let at an average of $500/m2.

OUTGOINGS -

Assume outgoings to be equal to $160/m2 today and subject to 4% annual escalation, with $5/m2 recoverable from tenants both office and retail.

FINANCING METHOD -

Option A - The Investment Company will have to borrow the capital, and it is to be assumed that the rate of interest will be 12% per annum compounded on a monthly basis.

Option B - Debt: Equity Ratio of 80: 20.

Option C - Debt: Equity Ratio of 50: 50.

THE ANALYSIS -

Part "A" -

1. Calculate total cost of the Development at 1st July 2018 value.

2. Preparing a development plan (including the sale of the apartments) by assuming that demolition; land development and design and construction will start on 1st October 2018.

3. Prepare a cash flow schedule starting on 1st July 2018.

4. Estimate the net income on completion of project, 1st July 2021

5. Calculate:

  • Total development cost.
  • Project finance cost.
  • Cost escalation.

6. Calculate the initial project development yield on completion of the project.

Part "B" -

Assuming the entire facility will be sold to John Wiley Pty Ltd. on completion (2021) at a price that will be 5% yield to John Wiley Pty Ltd. on the first year of ownership 2021. Calculate for John Wiley Pty Ltd.

1. The Price at which John Wiley Pty Ltd. will purchase the entire facility.

2. The original developer's profit/loss.

3. Generate an Annual Net Cash Flow for John Wiley Pty Ltd. for 10 years.

4. Net Present Value of the John Wiley Pty Ltd.'s cash flow using 9% discount rate (Base year 2021).

5. Assuming John Wiley Pty Ltd. sell the Facility for $900 million at the end of 10th year of ownership (year 2031), calculate the Net Present Value of sale. (Base year 2021). Discount rate is 9%

6. Calculate the Profit & IRR John Wiley Pty Ltd. will make at 2021 value.

Part "C" -

Assess the impact of changing the debt: equity ratio to 80: 20 and 50: 50.

Part "D" -

1. List all possible risks which may have an influence on this development proposal.

2. Identify three (3) key risk areas that need further evaluation from the above list.

3. Carry out sensitivity/risk analysis on the above three key areas which may have greater concern on the project development.

Part "E" -

List all assumptions at the front of your report.

Reference no: EM132245629

Questions Cloud

Optimal inventory policy relative to this toilet seat : Dingbat Manufacturing, Inc. (DMI) makes designer toilet seats. What is DMI's optimal inventory policy relative to this toilet seat?
Explain elements that relate to each of the four ds : In your description, be sure to identify and explain elements that relate to each of "the four Ds." Explain at least one cultural factor that may have impacted.
Show that average annual inventory carrying charges : Show that the average annual inventory carrying charges are equal to the average annual ordering costs when Q = Q*
Create three to five skills-based smart goals : Create three to five skills-based SMART goals for pre-practicum supervision. Have some stand alone lesson plans ready before the practicum.
Calculate total cost of the Development at July value : EPM5750 PROJECT INVESTMENT ANALYSIS ASSIGNMENT - City Highrise Complex Development Option, Victoria University, Australia. Calculate total cost of Development
Consider the deterministic production inventory model : Consider the deterministic production inventory model with no shortages allowed and a finite rate of inventory replenishment.
What is the diagnosis for kristopher : Kristopher is a 14-year-old boy who was recently accused by a female classmate of forcing her to have sex with him. He claimed that she agreed to have sex.
What’s your experience with benchmarking studies : What methods/metrics do you use to evaluate the organization’s progress? What’s your experience with benchmarking studies?
Mobile phones had on individual and collective reality : What impact has the internet, computers, and mobile phones had on individual and collective reality.

Reviews

len2245629

2/28/2019 8:38:28 PM

The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have been appointed as a financial consultant by an investment company to carry out a financial feasibility study for the proposed Office Development Complex Project. Prepare a report with your recommendations to the Director of the Investment Company to justify the financial viability of this proposed development. The final report due date is Week 10 – hand your assignment to your facilitator at the beginning of the class. After the submission you will be called for an interview to discuss your findings. This interview will be held within two weeks of your report submission. It is your responsibility to organise a time for an interview. If you fail to attend the interview, then the report will not be assessed and no marks will be given for this assignment.

Write a Review

Project Management Questions & Answers

  Create project objectives that have a measurable component

Create at least two project objectives that have a measurable component. Example of a program objective: Successfully launch 3 new products in the next 2 years.

  Managing stakeholder expectations and requirements

Review the Process Group and Knowledge Area matrix - identify key documents that you feel would be important to managing stakeholder expectations and requirements.

  Are the following two sample results significantly different

Relate the formula and identify each formula's components in the test of significant differences between two groups for when the question involved is.- Are the following two sample results significantly different?

  It project managers and traditional project managers

What is the difference between IT project managers and traditional project managers if there are so many similarities in project management discipline

  Explain the expected impact on the project

Explain the expected impact on the project, and suggest two ways the team could maintain its current goal in both planning and execution.

  Explain whether procurement documents should be rigorous

Explain whether procurement documents should be rigorous, flexible, or a combination of the two, and justify your answer.

  Unexpected operating system updates are soon be released

A software project is 50% complete. What should a PM do if unexpected operating system updates are soon be released?

  How would your current education and experience

In your response post, imagine you are applying for a position as the project manager for another student's company. How would your current education, experience, and skills support you in that role?

  Explain what result in given situation

McJunkin filed a third-party complaint against Alaskan, alleging that Alaskan was liable for any damages Mechanicals incurred as a result of the defective stub ends. What result? Explain.

  Recommend an eoq for macho heavy beer

Recommend an EOQ for Macho Heavy Beer. - Based on analysis of total variable inventory costs, is this offer attractive?

  Outline porters five forces model of industry competition

Outline Porter's five forces model of industry competition. How are the various barriers to entry relevant to global marketing?

  What is wrong with the managers actions

"I already know she can do the job. Why should I bother interviewing other employees?" What is wrong with the manager's actions?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd