The centroid of a square foundation of sides 5 m is located 10 m away from the edge of a vertical cut of depth4 m. The soil is a stiff-clay whose undrained strength is 20 kPa and whose unit weight is 16 kN/m3. Calculate the vertical ultimate load. Assume a circular failure surface for the footing and a planar surface for the cut.

Reference no: EM131137581

Questions Cloud

Determine the vertical deflection : Determine the vertical deflection at B and the member end moments at A and B for the beam in Figure. El is a consrtant.
Explore briefly the literature on adult attachment issues : Explore briefly the literature on adult attachment issues, considering that early influences can impact development across the lifespan
Determine the equation for distribution of shear strength : (Hint: Try a circular failure surface, determine the equation for the distribution of shear strength with depth, and integrate the shear strength over the radius to find the shear force.)
Level of significance to test the null hypothesis : In a study of the effectiveness of certain exercises in weight reduction, a group of 16 persons engaged in these exercises for one month and showed the following results:
Calculate the vertical ultimate load : Calculate the vertical ultimate load. Assume a circular failure surface for the footing and a planar surface for the cut.
Explains that needs to be revised in the assessment : Explains everything that needs to be revised in the assessment. - Just need supporting sources to back up what has already been stated in ALL THREE ASSESSMENTS.
Nine determinations of the specific heat of iron : Nine determinations of the specific heat of iron had a standard deviation of 0.0086. Assuming that these determinations constitute a random sample from a normal population, test the null hypothesis σ = 0.0100 against the alternative hypothesis σ
Determine the member end moments for the rectangular ring : Determine the member end moments for the rectangular ring in Figure, and draw the shear and moment curves for members AB and AD.
What is bottleneck activity and capacity of process : A small neighborhood restaurant is staffed by a hostess, five wait staff and four cooks. The hostess seats the guests and hands out the menu which takes 3 minutes. Then a waiter takes the orders and sends them to the kitchen which takes 5 minutes on ..

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the dynamic bending moment and deflection of rail

Develop practical and analytical understanding of the complex and multi-disciplinary nature of railways - Find the deflection and moment right and left side of center wheel

  Estimate of how many kbps would be required

(Note: there is clearly no "correct answer" here; the question is too vague for that. The point of the question is to get used to questioning objectives and approaches.)

  What is shear rate in water in sliding and standing plates

What is the shear rate in the water between a sliding and standing plate, if V = 10 ft/s is the moving plate velocity and 0.1 in. is the distance between the plates

  Determine how much power will be required above sea level

If I raise a 1000 lbf weight 100 feet above sea level on earth in 10 seconds how much power will be required

  Determine the induced emf within a circle of tissue

Transcranial magnetic stimulation (TMS) is a noninvasive techniqueused to stimulate regions of the human brain. A small coil isplaced on the scalp, and a brief burst of current in the coilproduces a rapidly changing magnetic field inside the brain. T..

  How much will be the contribution in the funds in 20 years

You are paying into a mututal fund that earns 6% compound interest. If you are making an annual contribution of $10000, how much will be in the funds in 20 years What if the fund makes 10% What if it loses 5% per year

  Determine the concentration of ubod in the effluent

If the length of the river connection between the two lakes is equal to 3km and the velocity in the river is equal to 0.4 m/s, determine the concentration of UBOD in the effluent from the second lake.

  Determine the benefit minus cost for proposal one

The problem belongs to Civil Engineering and it is describe the benefit minus cost for proposals for road improvement proposals in Bombay. Three proposals are being weighed for their maximum benefits, interest rate, value and cost, etc.

  What are the five branches of transportation engineering

What are the five branches of transportation engineering?

  Determine the normal stresses induced in portions ab and bc

A rod consisting of two cylindrical portions AB and BC is restrained at both ends. Portion AB is made of steel (E=29x10^6 psi, α=6.5x10^-6) and portion BC is made of aluminum (E=6.5x10^-6 psi, α=13.3x10^-6).

  Determine what is the effluent bod concentration

An activated sludge tank, 30 x 30 x 200 ft, is designed as a plug-flow reactor, with an influent BOD of 200 mg/L and a flow rate of 1 million gallons per day. a. If BOD removal is first-order reaction, and the rate constant is 2.5 days^-1, what is ..

  Determine the depth of a french drain-saturated depth

Determine the depth of a French drain (saturated depth) if the width is 3.0 feet, the effective permeability of the aggregate is 2000 ft/day, and the rate of discharge for 100 feet of trench is 1000 feet^3/day.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd