Calculate the uniformity coefficient

Assignment Help Civil Engineering
Reference no: EM131012959

1. The following data represent a mechanical analysis of Pleistocene glacial outwash from Kansas:

Size Grade(mm) Weight Retained(g)
19 30
9.5 18
4 28
2 35
1 30
0.5 16
0.25 20
0.125 15
0.075 10

a. Plot the particle size distribution of this figure.

b. Calculate the Uniformity Coefficient

c. Using the Unified Soil Classification System of the U.S. Army Corps of Engineers, classify the soil. (The fines are easy to crumble when dry and has rapid reaction when shaken.)

2. Give three reasons why bentonite (Na+ montmorillite) used for drilling mud instead of kaolinite clay?

Reference no: EM131012959

Questions Cloud

Find the curvature and radius of curvature of plane curve : Find the curvature and radius of curvature of the plane curve at the given value of x. (Give your answers correct to 3 significant figures.) y = 5x + 2/x, x = 3.
Evaluate organizational environment in health care industry : Evaluate the organizational environment in the health care industry to recognize how technology solutions enable strategic outcomes. Analyze the flow of data and information among disparate health information systems to support internal and externa..
Draw the shear and moment diagrams for the cantilever beam : Draw the shear and moment diagrams for the cantilever beam shown in the figure below. Label all values and units clearly and show all work when calculating shear forces and moments.
Find the equations for the tangent line of the graph : Find the equations for the tangent line of the graph f(x) = -x2 + 2x at x = 4. Performe the implicit differentiation to find the slop of the curve 2x2 + 3y2 = 5xy at the point (1,1).
Calculate the uniformity coefficient : Using the Unified Soil Classification System of the U.S. Army Corps of Engineers, classify the soil. (The fines are easy to crumble when dry and has rapid reaction when shaken.)
Write an expression that represents cost per movie rental : Write a rational expression to represent how much of the project Jan will complete in x hours - how much of the project will Rebekah complete every hour and Write a rational expression to represent how much of the project Rebekah will complete in x h..
Lyon declared dividends : Lyon declared dividends of $6,000 on preferred stock and $17,280 on common stock. At the beginning of 2013, 10,000 shares of common stock were outstanding.
Estimate the fatigue strength of a rotating-beam made : Estimate the fatigue strength of a rotating-beam made of AISI 1035 CR steel corresponding to a life of 10^5 cycles of stress reversal. Also, estimate the life of the specimen corresponding to stress apmlitude of 60 ksi.
Estimate the terminal velocity : Estimate the terminal velocity of a 1.5-mm plastic sphere in oil. The oil has a specific gravity of 0.95 and a kinematic viscosity of 10-4 m^2/s. The plastic has a specific gravity of 1.07. The volume of the sphere is given by piD3/6.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Water is transferred at a rate of 2.1cfs from reservior

Water is transferred at a rate of 2.1cfs from an upper reservoir to a lower reservoir by a concrete pipe 3000ft long. The difference in water level is 60ft. Determine the size of pipe for a water temperature of 60 degrees Fahrenheit. Apply The Darcy-..

  Determine the rankine earth pressure diagram

A ten-foot high wall will retain a medium dense sand backfill. Determine the Rankine earth pressure diagram and the total active force on the wall.

  Determine the modulus of elasticity of concrete by the aci

Determine the Modulus of Elasticity of Concrete by the ACI formula for a concrete cylinder that has a unit weight of 120pcf (1920kg/m^3) and a compressive strength of 3000 psi (21MPa).

  Plot the normalized concentration versus normalized time

Write the mass balance equation for a completely mixed lake with an impulse input of mass, M, added at time t = 0. Assume the lake is of constant volume, V, with continuous outflow, Q, and a conservative substance.

  How far above the hanging location does the target swing

A clay ball (m=0.82 kg) is thrown at a metal target (M=1.72 kg) that is suspended from a cable. The ball is released 1.5 m above teh ground at an angle of 32 degrees.

  Determine how much runoff reached the river for the year

The average rate of flow measured in a gage at the outlet of the watershed was 30 m^3/sec. Estimate the water losses due to the combined effects of evaporation, transpiration, and infiltration due to ground water.

  Determine the volume of soil that must be excavated

Soil have a void ratio of 0.68 as it exists in a borrow pit is to be excavated and transported to a fill site where it will be compacted to a void ratio of 0.45. The volume of fill required is 2500 m^3.

  Determine the elevation and stationing of the low point

A 1400-ft-long sag vertical curve (equal tangent)has a PVC at station 115 + 00 and elevation 750 ft. The initial grade is -3.5% and the final grade is +6.5%. Determine the elevation and stationing of the low point, PVI, and PVT

  Select proper value of k so that max deflection of spring

While designing a shock absorbing bumper for a 5-Mg rail car, the spring used for the bumper follows a nonlinear relationship of F = ks2 where F is the force in Newtons and s is the compression distance in meters.

  Estimate the mean and standard deviation of time

The probability density function, f(t), of the time in hours between storms during the summer in Miami is estimated as f(t) = .014e^(-.014t) if x > 0, f(t) = 0  if x is less than or equal to 0 where t is the time interval between storms in hours.

  Calculate the distance between two successive crests

A photograph is taken of a transverse wave travelling along a length of rope. At this instant the shape of the wave is described by y = (2 m) sin ((0.8 rad.m-1)x+0.8 rad). The speed of the wave is 2 m/s. Calculate the distance between two successi..

  Calculate what interest rate must the investment earn

A mining firm makes annual deposits of $250,000 into a reclamation fund for 20 years. If the firm must have $10 million when the mine is closed; what interest rate must the investment earn

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd