Reference no: EM132654695
Canadian tire company has the following standards for basket ball standard:
material (leather) per basketball .25 yard
material price per yard $16.00
direct labour hours per basket ball.2
wage rate per direct labour $18
variable support cost rate $15 per direct labour hour.
Actual results for the month
Amount of yards of raw material used$13000 yards used
purchasing cost of raw materials $205150
amount of direct labour hours used $8240 direct labour hours
wage rate per direct labour hour $17.50
variable support costs $131840
number of basketballs manufactured 40000
Problem 1: Calculate the following
a) total direct material cost variance
b) total direct labour cost variance
c) total variable support cost variance
d) direct material price variance
e) direct material quantity variance
f) direct labour rate variance
g) direct labour efficiency variance
h) variable support rate variance
i) variable support efficiency variance