Calculate the total transportation cost

Assignment Help Operation Management
Reference no: EM1398024

Problem 1 Facility Location

A big retail chain needs to find the best location to build new warehouse. The new warehouse will mainly serve on a weekly basis 8 stores in the northeast.

Using Euclidian distances compute the center of gravity and calculate the total transportation cost.

The following information has been collected for the 8 stores:

 

 

Rate

$/Ton Mile

Tons

Coordinates

 



x

y

A

1.30

300

700

1200

B

0.95

400

250

600

C

0.85

600

225

825

D

1.20

323

600

500

E

1.30

230

1050

1200

F

0.80

120

800

300

G

0.90

400

925

975

H

1.23

300

1000

1080

Problem 2 Facility layout

Assume the following office plan among different departments.

1199_Materials Requirements Planning.png

The average number of contacts among departments per week is indicated below:

 

Adm

R&D

Prog

Design

Sales

Cons

Adm

-

2

8

6

20

10

R&D

 

-

30

50

40

20

Prog

 

 

-

50

10

70

Design

 

 

 

-

20

30

Sales

 

 

 

 

-

50

Cons

 

 

 

 

 

-

Compute the total "load-distance" LD score for the current solution, and then try to find an improved layout.

Problem 3 Materials Requirements Planning

A manufacturing plant produces an end-item A, according to the following bill of materials:

2259_Materials Requirements Planning1.png

The MPS for the end-item A is given in table 1. The manufacturing / assembly lead times, the lot sizing rules, and the current on-hand inventory for all constituting items are given in table 2. There are scheduled receipts for item C at week 1 (100 pieces) and for item D at week 3 (80 pieces).

Table 1: MPS Quantities

MPS Quantities

1

2

3

4

5

6

7

8

9

10

Gross Requirements (Α)

-

30

-

50

-

200

-

120

180

60

Table 2: Lead times, lot sizing rules, on-hand inventory

Item

Lead Time

Lot sizing rule

On-hand inventory

A

2 weeks

Lot-for-lot

40

B

1 week

Fixed Order Period = 3 weeks

20

C

2 weeks

Lot-for-lot

20

D

3 weeks

Fixed Order Quantity = 500 units

300

Determine the material requirement plan (fill the following tables).

Item: A

Production Lead Time: 2 weeks

Lot size rule:  Lot-for-Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand       40

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 













 

Item: B

Production Lead Time: 1 week

Lot size rule:   FOP (P=3 weeks)

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand       20

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 













 

Item: C

Production Lead Time: 2 week

Lot size rule:  Lot-for-Lot

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand     20

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 













 

Item: D

Production Lead Time: 3 weeks

Lot size rule: FOQ (Q=500)

Week No.

1

2

3

4

5

6

7

8

9

10

Gross Requirements

 

 

 

 

 

 

 

 

 

 

Adjusted Scheduled Receipts

 

 

 

 

 

 

 

 

 

 

Projected on-hand     300

 

 

 

 

 

 

 

 

 

 

Net Requirements

 

 

 

 

 

 

 

 

 

 

Planned order receipt

 

 

 

 

 

 

 

 

 

 

Planned order release

 

 

 

 

 

 

 

 

 

 













Reference no: EM1398024

Questions Cloud

Two way anova with interaction in statdisk : Set up the following null and alternative hypotheses for both factors and their interaction. You should have three verbal statements, not symbolized statements.
Finding lod score for association in chromosomal location : Parkinson disease (PD) is a neurodegenerative disease that has been associated with a significant number of different genes, therefore showing it to be genetically heterogenic.
Family spending per year on dental expenses : The Human Relations Department of Electronics Inc. would like to include a dental plan as part of the benefits package. The question is: How much does a typical employee and his or her family spend per year on dental expenses?
Example of repeated measures analysis of variance : Give an example of a repeated measures analysis of variance (ANOVA)--no examples of therapy or temperature.
Calculate the total transportation cost : Compute the total "load-distance" LD score for the current solution, and then try to find an improved layout and calculate the total transportation cost.
Is chromatography a valid method : Is chromatography a valid method for identifying amino acids from an unknown mixture like serum? Wht or why not.
Write the difference between correlation and causation : Write down the difference between correlation and causation. How would results of this survey be used in workplace?
Post translational modification in the er : Which of the following is NOT the way proteins are transported through the Golgi? Clathrin-coated vesicles bud from the ER and fuse with the Golgi.
Percent confidence interval for the population mean : A recent survey of 50 executives who were laid off durning a recent recession revealed it took a mean of 26 weeks for them to find another position. The standard deviation of the sample was 6.2 weeks. Construct a 95 percent confidence interval for..

Reviews

Write a Review

Operation Management Questions & Answers

  Explain how you would approach the process

explain how you would approach the process. Keep in mind which you are supplying a major automotive organization which manufactures, on average, 835,000 cars per year.

  Determine upper control line quality control purposes

You need to determine upper control line for a "p" chart for quality control purposes. You take several samples of a size of 100 items in your production process. From samples you determine.

  Which approach is preferable to ms morgan

South-eastern Airline's daily flight from Atlanta to Charlotte uses a Boeing 737, with all-coach seating for 120 people. Which approach is preferable to Ms. Morgan.

  What order quantity minimizes total annual inventory cost

They sell 100 printers per month. The manufacturer has offered the following price schedule. What order quantity minimizes total annual inventory cost?

  How many laborers are employed at the plant

If the labor productivity at the plant is 0.15 hot water heaters per labor-hour, how many laborers are employed at the plant?

  Belief which helps solves difficult social problems create

Belief which helps solves difficult social problems create a desirable community also attract also keep skilled employees is known as which argument.

  Determine the approximate length of a production run

Determine the approximate length of a production run in days. About how many runs per year would there be?

  Develop a linear programming model that will enable hts

Develop a linear programming model that will enable HTS to allocate technician time between regular customers and new customers. Find the optimal solution.

  Find out the economic run size and maximum inventory

Candles can be produced at a rate of 36 boxes per day. The shop operates 20 days a month. Suppose that Demand is uniform throughout the month. Setup cost is $60 for a run also holding cost is $2 per box on a monthly basis.

  Evaluation and synthesis

Imagine you are the marketing manager responsible for developing marketing strategy for a bicycle company. Propose the strategic marketing process you will use being sure the name the stages, the activities included in the stages and stage specifi..

  What steps would you suggest to manage the transition

What steps would you suggest to manage the transition from the old organizational structure to the new, How would you assess the external environment and integrate this into the turn-around plan

  Do you see any flaw in arguing which organizations

Do you see any flaw in arguing which organizations don't have expertise to assess also make decisions about worthy social programs also therefore y should not get involved.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd