Reference no: EM13321947
Which of the following will correctly calculate the total slack in an activity?
A) Late Start - Early Start (LS - ES)
B) Late Finish - Early Finish (LF - EF)
C) Late Start - Late Finish (LS - LF)
D) Late Finish - Early Start (LF - ES)
E) Both A and B are correct
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
A) Check to see which activities cost the least
B) Check to see which activities have the longest duration
C) Check to see which activities are on the critical path
D) Check to see which activities have the most slack
E) Check to see which activities have the highest risk
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct
If testing cannot be completed any earlier than four days after the prototype is built, which of the following type of lag exists?
A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct
Nodes on an AON project network represent:
A) An activity
B) An event
C) Responsibility
D) Both B and C are correct
E) Both A and B are correct.
Briefly describe various types of negotiable instruments
: Briefly describe various types of negotiable instruments. Why might a person choose one over the other?
|
True about work packages
: All of the following are true about work packages except: The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers.
|
Appear on a project scope checklist
: The lowest element in the hierarchical breakdown of the WBS is: "To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as: Which of the following is not one of the items that would appear on a..
|
Example of an organizational process asset
: Which one of the following is not an example of an Organizational Process Asset? The first step in creating the necessary information to manage a project is to: In Microsoft Project, if a resource is scheduled for more work - in a given time period -..
|
Calculate the total slack in an activity
: Which of the following will correctly calculate the total slack in an activity? If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? Nodes on an AON project n..
|
The critical path in a project network represents
: The critical path in a project network represents the: Activities which can take place at the same time are termed: The backward pass in project network calculations determines the: The amount of time an activity can be delayed and yet not delay the ..
|
Bottom-up approaches for estimating project times and costs
: Which of the following are not bottom-up approaches for estimating project times and costs? Which of the following is not one of the recommended guidelines for developing useful work package estimates? Reasons why estimating time and cost are importa..
|
Quality of estimates for project times and costs
: Which of the following is provided by a project network but not by the work breakdown structure? On a project network, the activity times are derived from the: Which of the following is not one of the factors that need to be considered to improve qua..
|
What are potential benefits of recognizing
: What are potential benefits of recognizing and eliminating non-value added activities for businesses?
|